Hello everyone
This is Pavel Sidorik your host as always with a channel about repairs
and renovations
The topic of today's video is the subtleties of working with a screed
I' ll show you an interesting technique
that will allow you to from a screed
Make a thin layer screed from ordinary concrete mix
My home repair is gradually moving to the balcony
It's time to do the screed here
Using this work as an example I will explain what difficulties
may arise and how to solve them
And some nuances that will help you
make a smooth high-quality screed
I have made a lot of repairs in my time and also done a
lot of repairs on behalf of other professionals in quotes
And I never stop telling my clients that plastering
and rendering are the foundation of any renovation
These works can be compared to a car The body is the plaster
and screed and everything else
that is added is different work
A car cannot be good by
definition if it has a bad body
If the foundation of your repair
is poor all subsequent work
will also be done poorly There will be many inconsistencies
What are the consequences of poor tiling
First of all it will affect all floor coverings
Laminate and parquet flooring will be installed on the floor and
will accordingly break the locks and the boards will spread out
The tile will be laid on a layer of adhesive this is certainly
not the same quality if it were laid with a notched trowel
There will be gaps when installing baseboards
Problem with installing door frames - floor coverings
They can be of different types and will be at different levels
You will get sills and small steps
Just the furniture will be wobbly and unstable
you'll have to put rolled-up paper under the legs
And this is just part of the problems you may encounter
Now let's move directly to the points that
you need to consider
All foundations from developers are almost always crooked
This applies to all types of houses – monolithic-frame
panel brick as well as all types of screeds
These are mainly classic screeds that are poured
Wet and dry troweled screed when the concrete
pump delivers the semi-dry mix to the site
If your home is rented unfurnished there
are no issues here
The height of the ceilings and the monolithic floor allow
you to make any type of screed
As a filler you can choose extruded
polystyrene or perlite or if you have a base
If you add more bitumen sound insulation
your neighbors below will be praying to you
You just need to find skilled craftsmen
How to find them is another question it's even a separate
topic for a video
There is a 4 square meter
deflection of the slab on my balcony 7 centimeters
But most often
the houses are rented with
a finished screed Here are three options
The first option is to apply a thin layer of
screed throughout the apartment about one to one and a half centimeters
The second option is
to grind down the bumps if the curvature of the screed allows
The third option is to dismantle what is there
remove the debris and pour a proper thick screed
It is mainly used in expensive repairs
where money is not the main issue
Let's focus on the most common thin-layer
screed which is used in almost 80% of cases
What material should the screed be made of
There are now many thin-layer floors on the market
It's like a self-leveling floor but in reality it's
hard to cover a large area with this type of floor
It is possible but there are many complications and a high price
The result may be unsatisfactory
Therefore when I need to paint the entire apartment
in one level I don't use these compositions
Now manufacturers make standard cement-
sand screeds that can be poured from 10 mm
But on the last two sites
I found a better and more advantageous
option This is concrete mix that can also be poured from
10 mm it is 1.5 times cheaper
A 40 kg bag costs 120 Russian rubles 4 Belarusian rubles and
The screed costs 135 rubles for 25 kilograms
and in Belarusian it will be 5 rubles
In addition the concrete has a strength of
M300 which allows for pouring industrial floors
I got to know this cement
mortar when we did the screed with sound insulation
The purpose of the insulation is to lay down stone wool
cover it with a tarp and then pour a monolithic layer on top
A plate with a formation of 5 cm and more
There they use the M300 mixture
and had to buy sand concrete
I liked him
A few tips on how to choose high-quality sand concrete
Buy sand concrete from the cement manufacturer
How to check it is simple go to the company's
website and see what its main area of focus is
Concrete mix should be the color of cement not sand
It should not separate when mixed
and there should be
no situation where there is a thick sediment at the bottom and water on top
This indicates that there is
only sand and a small amount of cement
When purchasing the material make sure to check that there is no
Sometimes building materials
are stored incorrectly
We start pouring the screed by removing all
the trash and thoroughly vacuuming the floor
We prime the base thoroughly not sparing the
primer After that we wait
for it to dry completely
Time is usually written on the packaging
We foam all
the gaps on the balcony with construction foam
Otherwise the mortar will leak through them
It is necessary to sand the
base before pouring the screed and then thoroughly prime it
I often encountered situations where people reason like this:
if the coating is poured then there's no need to clean it
Just flush all this dirt away
In reality it turns out that those places where there was dust
And the sand they start to crack the screed does not adhere in those places
At which stage is the screed poured
The screed is poured
after the plastering work is completed
The room's geometry is displayed a damping tape is
applied around the perimeter and a screed is poured
The damping tape must be applied it compensates
for thermal expansion plus serves as a seal
A sound insulator
Vibration from the floor you walk on is not transmitted
It does not transfer to your neighbors respectively
As a damping tape I often use a backing
It is easy to work with
extruded polystyrene laminate
For a regular room and a full screed the
thickness of the tape should be 10 mm
For small spaces or thin-layer
screed a 5 mm tape can be used
Using a painter's knife cut the backing into strips
We attach the strips to the wall with silicone applying
the silicone to the bottom of the strip that will remain in the clamp
Let's move on setting beacons I am setting the beacons on the
plaster this allows them to be
installed quickly and accurately
The beacons should be installed on the
same base the same concrete mix or screed
But it's inconvenient
The anchors fall off the mixture takes a long
time to gain strength and slows down the work
There are many armchair experts on YouTube who make
comments about this but in practice all the masters are
They practically install beacons on the plaster
I have never once seen any consequences from this
problems in the process of
further use of the screed To set
the guides you need to find the highest point
I use a laser level and a square for this
We measure the area of the entire room as I said
On such a small area the difference was 7 centimeters
If the thickness of the screed allows it is better to use guides
10 millimeters they are harder
Where the screed will be 8
centimeters I place penoplex under the guide
It's easier to set the
guides they won't float on the plaster
Mix the plaster
I start installing the guides using a laser level
and a square
In my videos I have already shown this technology
which allows you to set beacons quickly and accurately
When pouring the screed the thickness of all must be taken into account
floor coverings that will be tile thickness parque
boards laminate and also take into account underfloor heating
Before pouring the screed it is advisable to prepare
Samples on the object one board one tile so
the craftsmen can actually see how it turns out
And set the markers at different levels
Then you will have a single-level finish
without thresholds and steps
On one side the screed was 8 centimeters and I threw the
remaining polystyrene foam in there and on the other side
Less than one centimeter
If you don't have a ruler of the required length for narrow sections
It can be cut it is a consumable
The length should be slightly less than the width of the room
Why do thin-layered screeds
crack and delaminate from the base
Because the water quickly evaporates from them the
solution dries out and does not have time to gain strength
Here you need to either water the concrete or cover it with plastic but
this does not always help There is a simple
method that will allow a regular mixture
Pour a thin layer of 10 millimeters
Before pouring the screed brush the base with tile adhesive
Use a comb to make grooves
The glue will create an adhesive layer that will firmly bond the screed
and the base
Plus the glue holds water well and
no water will escape from the mix
You can also mix mortar with
tile adhesive on thin sections
Use a mixture of 70%
cement mortar and 30% tile adhesive
This will allow you to stretch especially thin areas
The glue will provide elasticity and hold water and
Concrete mix will provide strength and the mortar will not settle
Thin areas are brushed with tile adhesive
Then I comb it creating a groove on the base
Modern technology allows for pouring a screed with
a 2 millimeter difference throughout the apartment
We mix the concrete mix twice with a 5
minute interval and start pouring the screed
In small rooms there is especially nowhere to move around
Especially if the apartment is residential
The day after the concrete has been poured while the
concrete mix has not yet gained strength it can be
Trim and remove the ridges
This must be done
Do we need to retrieve the beacons
In theory yes but in practice there are two methods
where beacons are retrieved and where they are not
When you pour the screed the next day it slightly
settles and the guides end up sticking out a bit
Then you cut the screed along the guidelines then remove
Lamps from the floor again you trim and then fill the grooves
Another way is to do the following after trimming
Spread a thin layer of tile adhesive along the
guides to compensate for the settlement of the screed
This is especially relevant if the beacons are
set precisely and you need a certain thickness
Cement-based mortar gains its strength over
28 days so it needs to be cared for and watered
Cover with water or with a plastic sheet A
plastic sheet is preferable because accordingly
You don't need to come to the site to water it
and plus excess humidity does not get into
The apartment because the film creates a barrier
I water it abundantly and cover it with plastic
The slab is ready
now it remains to wait until it gains its strength
Friends thank you all for your attention the video has come to an
end If you liked
it of course give it a like
Subscribe to the channel and leave comments
Have a great day see you next time