Have you ever heard someone say that house has good bones?
What are they talking about? Of course it's the framing.
Super important for a well-built house to start with a well-framed house.
On the build show today we're going to talk about advanced framing versus traditional framing
and go beyond the typical discussion which is just should I frame my house on 16-inch
or 24-inch centers like you see here. I've got a special guest for today's build show. Let's get
going. All right guys let me introduce you to my friend Steve Basic. Steve you're the architect
on this project and I want you to tell us a little bit about why you chose to do advanced
framing on this particular house. All right so we're going to start out with a little pet peeve
because you already pushed the button on me man. So advanced framing let's just call it smart framing
because there's traditional framing, advanced framing, all these different kinds of framing
packages but I like to look at it as the framing is just one of the systems in the house and for
particular projects you need a particular system and so in this case here you know a 24-inch on
center framing system worked just really good with what the system overall package was here so
we can call it advanced framing call it whatever you want but it's really about making decisions
that are appropriate to the overall decision being made on the project. I love that so you
know when I hear advanced framing sometimes I think oh we're trying to save lumber or save money
but in reality it's being smart and designing it from the start. Now let's talk about this house
Steve this is what a 2,400 square foot house ish plus we're actually in the garage right here.
500-600 square feet of garage here good size. Okay so 3,000 or so feet under roof on this house
and in this particular case we've got trusses above us here which are actually landing front
to back on the house so we're clear spanning the garage here we've got no posts in the garage.
No posts in the garage no posts in the house so the whole house load is brought down to the
outside walls which is where the outside foundation wall system is so it was inevitably the decision
when I you know working with the builder Jake and we came up with the idea let's let's frame
up those outside walls let's throw the roof on there get it closed in with some zip sheathing
get us nice and weather tight real quick but now we have a factory to do everything else inside
here so when guys talk about oh you know it's better to do things off-site and you get better
quality well if we build a little warehouse here then we can control the environment and get good
quality on everything we do inside. So true it's like a little barn isn't it I love that.
All right so then talk to me about some of the details on this framing so we've got 24 inch
on studs on these outside walls 24 inch on center framing right all the studs align with the trusses
up above okay we have our trimmers come down notice we don't throw the extra jack in here
they actually take the time to cut the cripple set the sill okay and then run the trimmer up
above that so it eliminates a little inside of that gotcha and then that goes up to our header
I always insert a header plate on the bottom that helps us catch all the trim and stuff on
the windows but then notice that we do an appropriately sized header and then that
creates a header pocket. Yep so LVL header right there and then that plate right there that's your
two by six that you're using underneath that header so now our trim and everything is going
to sit flush. It's going to sit flush but the beauty of this is you know I always talk about
the framer gets to do what the framer does when the framer should do it so we're not out of sequence
and then the insulator when he comes he can insulate that pocket when it's time for an
insulation to go in and the insulator does what the insulator does when he needs to do it yeah so
we're not asking somebody to come and just spray that we're not asking the framer to mess around
with two inches of rigid foam and build insulated headers we get what we get through the normal
sequence of stuff. Now Steve I'm also noticing now it looks like the insulators coming a little
early but your your trusses seem to be quite a bit higher over that top plate what's what's
what you see up there is the truss industry calls that a slider so you notice that we basically took
a two by six and we split it down in between the joint of the bottom cord and upper cord and what
it does is it basically splits those cords and it elevates the heel height so we get a little bit
more insulation above the wall which is traditionally you know the bad decision of just having that
little throat dimension of like four inches is now 10 inches so we get really good adequate
insulation above our wall plate. All right now I'm noticing you've got double top plates here
and a lot of times when I read about advanced framing they're preaching single top plate as
little lumber as possible what's the difference between the single and the double up there? So
again when we look at this the system as a whole we will come to understand that the sheathing on
the outside is our sheathing right so that means we have a one inch poly iso panel that sits on
the outside of the house okay and because of that then we've picked up some of the losses of the
thermal efficiency in the house by simply having that our sheathing on the outside of the house.
Gotcha. So because we do that then I don't have to nickel and dime the framing package
and beat up the framers this particular framer who does an exceptional job he likes the double
top plate because it does it helps him straighten out his walls and it's keeps him in you know a
traditional mindset but we're still building a a wall that's better than what's traditionally
built. Got it so these walls in here are what 10 foot tall is that right? Yeah they're well they're
nine foot walls ten nine foot ceilings from the plate to there. Gotcha and then I'm seeing these
two sheathing breaks here I don't normally see those in this location what's going on with that?
Yeah so we we couldn't get the 10 foot zip art panels here so what the framer chose to do is
keep that blocking in a comfort range right so they're not working off the ladders or scaffolding
to deal with the joints so they railroaded the lower piece they railroaded the upper piece and
then they put that joint in the middle so now all of the blocking and stuff is done at a very
convenient level. Got it that makes sense now tell me about this hardware I'm seeing over this big
header on this window now this window just for clarity hasn't been cut out yet check out our
other videos about why but talk to me about that clip right there Steve. So that's just a simple
header hanger if you notice that we went down to a single jack here in the code and you know
window openings over three feet would require a double jack okay but one way we eliminated that
other jack was to simply put in that header hanger there which adds assistance to carrying that
header. Gotcha that makes sense and then tell me about insulation for these cavities later because
you've got this big five and a half inch deep cavity plus we talked about the zip R which is
one inch thick that's going to give you R6.6 on the outside then what are you going to do
inside the wall? So on the inside we're going to splash it with an inch of closed cell foam
okay we'll probably bring that up a little bit and then we're just going to fill the rest with
a blown fiberglass blown in back package I mean this this is a house that you know we we care
about the decisions but it's still a house that's kind of in that commodity realm where we're showing
people that you can build the average house really well yeah right that you don't have to go over the
top to build it to get a really good house and honestly the the R6.6 outside is more important
than anything we put in the cavity right right because you've got a you've got all that continuous
on the outside without any breakage because each one of these studs is probably around R1 per inch
well yeah R1 I there are sorry two by six stud is about R5.5 okay right so when you look at a
wall system if we were able to take all of the exterior walls in this house and make them one
wall all right that would suggest that about 20% well probably about 18% is framing okay and that's
R5 ish right right 63 64 is cavity so that's your true R value in the wall and then another 20% ish
is windows and these these windows are better than your usual you know point three windows
these are going to be closer to R7 R8 windows they're triple glazed so we elevate that but
understand that those three major components that make up a wall the minute I put R sheathing on
the outside it improves the 60% of the cavity area but it also improves the 20% of the opaque
area where the framing is and it effectively more than doubles the R value at the opaque framing
so when you normalize those values it brings your R value way up right I had one of the best
building scientists I've ever met and I sat down at lunch with him one day and I said hey Gus what
what's the best wall we can build you know what give me the skinny here I'm a young architect I
want the secrets right he said it's real simple put as much insulation as you can afford on the
outside of the house and never go wrong smart really smart Steve anything I missed on the topic
of framing in particular in this house that you wanted to mention no I mean but you know as we
look at the expanse you know again you can see that because we're carrying it from wall to wall
it gives you this factory environment to do everything you know when we were able to do
some good air sealing details I know all this stuff you're going to pick up in some later videos
but it's just kind of creating that enclosure so that we take an on-site construction project
and make it more like a factory built environment because we inevitably built our on-site factory
so awesome guys for more on this project this is called the hybrid house right yeah sure
Steve's the architect my buddy Jake Bruton with Arrow Builders in Columbia Missouri is the builder
here and Jake is brand new on our network that we've just come out with so if you don't know
about that go to buildshownetwork.com you're gonna have several videos including several with Steve
telling you the behind the scenes on this house there's a lot of technology behind this house
that's not expensive it's just smart and Steve and Jake did an amazing job in designing and
building this house and doing on a really reasonable budget of under $250 a square foot
for this house for some amazing both scores and performance and products going in here
but really off the shelf stuff so go to buildshownetwork.com follow Steve on Instagram
we'll put a link in the description if you want to see more of Steve's work too we actually shot
a bunch of videos with Steve from Boston where Steve is based out of so I'll put a link in the
description to those as well Steve's built several passive houses and some amazing projects if you're
not already a subscriber though hit that subscribe button below we've got content every Tuesday
and every Friday follow us on Twitter Instagram otherwise we'll see you next time on the Build Show!