In the early 1960s, a cynical British commentator remarked that a motorway could be defined
as the shortest distance between two traffic jams, and that cynical dude was absolutely
correct.
In the 1980s, France had a slightly different problem.
Two motorways from opposite directions, leading to the same traffic jam, Mio.
Situated at the bottom of one of the deepest valleys in Europe, the medieval town, the
center of the ceramics trade in Roman times and with its roots back in the Bronze Age,
must have always been a difficult place to get to, through, or round.
In the 20th century, it was on the most popular holiday route in the country, Paris to the
Mediterranean, and regularly it suffered five or six-hour traffic jams throughout July
and August.
The high-speed routes to the north and south stopped short at the chasm that was the town
valley.
How to bridge the gap occupied the minds of planners, engineers, and architects for the
best part of two decades.
Four possible routes were considered.
The road could bypass Mio to the east, crossing the Tarn and the Dubie rivers on two very
high bridges with spans of 800 and 1,000 meters, respectively.
These posed technical problems, but the main objection to this route was that Mio would
basically be virtually cut off from the outside world.
A bypass to the west was technically easier, but more expensive and 12 kilometers longer.
The main drawback to this solution was the adverse impact on the environment, a factor
that was particularly important considering the spectacular beauty of this area.
A third suggested route was rejected because of its possible impact on future plans for
the area, leaving the fourth possibility, also to the west of Mio, crossing not only
the river, but the entire valley of the Tarn as the preferred route.
This could be accomplished in one of two ways, a descent into the valley followed by a bridge,
a viaduct and a tunnel, or the seemingly impossible, a 2.5 kilometer long viaduct more than 200
meters above the river.
They chose the impossible.
Fresh from the success of his Pond Normandy at the time the longest cable-stayed bridge
in the world, Dr. Michel Villegot had ambitious plans for Mio.
While the Normandy bridge had cable stays on both sides of the road deck, his concept
for this viaduct had just one central set of stays and would be carried by not two,
but nine piers right across the valley from the plateau on one side to the plateau on
the other.
Unwilling to take a chance on one man's ideas, the French Roads Administration announced
a competition for architects and engineers to come up with a practical design.
By July 1993, the applications by 17 engineers and 38 architects had been whittled down to
eight structural engineers and seven architects to study the problem.
Between them and an independent panel of experts, they came up with five general design ideas
by February 1995.
The competition was re-launched with five engineering-slash-architectural partnerships
doing in-depth studies of the selected approaches to the problem and, in July 1996, the multiple-span
cable-stayed viaduct proposed by the structural engineering group Sogallerg-Europe-Etudes-Guetzi
and Cerf with British architect Lord Norman Foster was selected.
Foster had taken Villegot's concept even further into the realms of the impossible
by cutting the number of piers to seven and making them even slimmer.
The basis of his thinking was to take an inventive piece of engineering and turn it into a work
of art, something that would appear to rest lightly on the incredible mountain landscape.
The next two and a half years saw extensive studies being made so the intricate details
of the design could be finalized.
A geological survey showed that the fractured limestone, coupled with a myriad of caves
in the area, might pose a problem in the form of landslides, while an 18-month meteorological
study showed that the wind being funnelled through the gorge could gust up to 130km an
hour.
Hurricane forces.
Wind tunnels led to alterations in the shape of the road deck and some detailed corrections
being made to the shape of the pylons, but by late 1998 the final design was approved.
The project went out to tender in 1999 and was awarded to Compagnie Effage du Viaduc
de Millau.
Now, all they had to do was build the tallest bridge piers in the world and put a 36,000-ton
freeway on top of them.
No worries.
Oh, and that was just for starters.
Then they had to erect seven steel pylons, each weighing 700 tons, and secure the road
deck with 5,000 tons of pre-stressed steel cabling.
And they had to do it in under four years or face a fine of $30,000 a day for late delivery.
Even some of the engineers on the project had their doubts.
Two weeks after the laying of the first stone, on December 14, 2001, the workers started
digging the shafts for the pylons, four to each pier, 15 meters deep and five meters
in diameter.
The footings on top of the concrete pylons took another 2,000 cubic meters of concrete
and now progress began to show above the ground.
Now, back to our video in just a moment, but first, a word from today's video sponsor,
Squarespace.
Right now, it's the age of creation.
Think about it.
Everyone is out there online making something.
And chances are, you've got a great idea yourself, or you probably know someone who
does.
And when it's time to move that project from your head to the screen in front of you,
that's where Squarespace comes in as the perfect web tool to help you fashion the internet
into whatever you like.
Maybe you're the hands-on type, with lots of opinions and ideas about what exactly your
website should look like.
If so, fantastic!
Squarespace gives you all of the customization options you could ever want.
No updates, no patches, no technical nonsense to worry about.
Or maybe you just need something functional, something that works with minimal thought
so you can stay focused on the content and not just the coat of paint.
Well, just use one of their quick, beautiful templates to make a website that's both fresh
and for you.
And once you're done setting up your website, logging in the name, maybe playing with some
of the colors, there are so many extra features that Squarespace provides so that your website
can thrive.
Email campaigns.
Patronage portals.
Social integrations.
Member-only areas.
Analytics.
Commercial options.
24x7 customer support.
It's everything you need in one place.
So when you're ready to get started on the next project of yours, big or small, if it
involves a website, you gotta do it with Squarespace.
Right now you can go to squarespace.com for a free trial and when you're ready to launch
your new site, go to squarespace.com forward slash megaprojects and you'll save 10% off
your first purchasable website or domain.
Every three days, each pier grew by four meters.
Then, because of the tapering design of the piers, the 15-ton mold had to be taken down
and adjusted for the next pour.
The concrete was being manufactured on-site, so a new layer could be poured every 20 minutes
and the speed of construction increased rapidly.
Now, it was during this phase that geologists' fears were realized.
A violent storm caused a landslide and 4,000 cubic meters of rock were dislodged near the
first pier.
Fortunately, the pier wasn't damaged, but manpower had to be diverted to stabilizing
the ground and time was of the essence.
Construction continued, with each team aiming its pier to an exact point in the sky.
With no visual reference as to whether the piers were straight, the engineers relied
on GPS using multiple satellite feeds to pinpoint the destination of the build.
By November 2003, the piers had reached their full height a month ahead of schedule and
accurate to within two centimeters.
Meanwhile, the steel company Iffel, founded by Gustave Iffel of Eiffel Tower fame, was
manufacturing the steel road deck.
The 2,200 separate sections, each weighing up to 90 tons and some as long as 22 meters,
then had to be transported hundreds of kilometers by road and welded together on-site.
The plan was to slide the two colossal sections across the piers from either side of the valley
so they would meet in the middle.
To stop the leading edge from dipping and knocking down the piers, one of the pylons
was installed on each section to hold the cable stays supporting the front of the deck.
Temporary steel support towers were then placed at each halfway point between the piers to
make the distance between them more manageable.
Even so, the road deck would still have to be launched over greater distances than had
ever been done before.
Also, simply launching the sections over the edge by pushing them with hydraulic jacks
was not going to work in the case of such enormous sections.
The jacks would need a considerable amount of help along the way.
The engineers designed a novel system of pairs of hydraulically driven wedges, four sets
of which were installed on top of each pier.
The upper and lower wedge of each pair pointed in opposite directions.
Controlled by a computer so that they acted in perfect unison, the lower wedges were to
slide under the upper ones, forcing them high enough to lift the road deck off of its supports.
Both wedges would then slide forward, moving the deck forward.
The lower wedges would then return to their starting positions, followed by the upper
wedges, leaving the deck 600mm further along its journey.
Then the four minute cycle would be repeated.
No launch had ever been done this way before, and there was no chance to test the system.
It just had to work.
And it did.
And everything went smoothly.
Until six months into the launch, when one of the launch systems failed.
To make matters worse, the meteorologists were predicting a storm and the deck was in
a vulnerable position, with its leading edge hanging out into space.
The engineers had underestimated the friction between the sliding surfaces of the wedges
and the non-stick PTFE coating which had worn away.
There were no spare parts for this impromptu design, but there were as yet unused pairs
of wedges which were destined for the piers that had yet to be reached by the advancing
deck.
The team hastily stripped them of their coating and repaired the damaged units, while the
weathermen chewed their nails and monitored the impending storm.
Disaster had just been averted.
The deck reached its next support safely.
Over the next months, the two sections of the deck edged towards each other.
As each reached its next support, the teams breathed a collective sigh of relief and checked
the weather forecast before pushing on to the next stage.
Things were going well, but there was still no guarantee that the two sides would meet
in the right place.
Even the slightest inaccuracy could mean that they'd built the most expensive white elephant
in Europe.
The engineers installed a GPS system on the leading edge of the section that was to make
the final push, so they could compare the actual position with their calculations.
They now approached the most difficult part of the launch, bridging the river itself.
Not only was this the longest span of the viaduct, but it was also the one place where
it had been impossible to erect any intermediate supports.
The leading edge of the longer section launched across 342 meters of open space, and the teams
held their breath as the suspense mounted, and the French Prime Minister was also due
to drop by to see the event.
No pressure.
As the edges got closer together, the tension eased.
It looked as if it would be a near-perfect fit.
A magnum of champagne was positioned at the point of contact, and as it exploded, other
corks were popped.
Celebrations were in order, because the discrepancy in the alignment was a matter of millimeters.
Of course, the project was nowhere near complete, but the first two major challenges, the piers
and the road deck, had been successfully navigated, and were still on schedule.
Because steel is flexible, more so than some of them had realized, the road deck had an
undulating appearance at this stage that was a bit of a cause for worry.
Would the cable stays pull it straight, or had they run across another unexpected problem?
Before their question could be answered, the remaining five pylons had to be erected.
These 700-ton steel monsters had to be raised through 90 degrees, and accurately positioned
on top of the piers.
To achieve this, they borrowed a 2,000-year-old technique from the ancient Egyptians, who
had used it to erect obelisks and piers at Karnak.
While the Egyptians would have used slaves as their motive power, the 21st century engineers
had the advantage of hydraulics to lift this massive weight.
The principle was straightforward.
As Archimedes summed it up,
Give me a lever long enough on a fulcrum, and I'll move the world.
On top of the road deck, the team put up two enormous towers, secured by cables and equipped
with a hydraulic system capable of raising 1,000 tons.
As the hydraulics lifted each pylon, it pivoted slowly until it was vertical and could be
lowered safely onto its anchoring point.
With all seven pylons in place, the team attached the cables which supported the deck.
As the tension on the cables increased, so the kinks in the road deck smoothed out, and
another challenge had been met.
There just remained the finishing touches.
The road surface added 10,000 tons to the weight of the deck, and just to be sure it
was safe, they drove 36 monster trucks with a combined weight of over 900 tons onto the
longest span.
The distortion was negligible.
On December 14, 2004, President Jacques Chirac formally opened the viaduct, and it opened
to traffic two days later.
The construction of the Minot Viaduct broke several records.
Two of the piers were the highest in the world.
The pylon on top of the second pier was the highest bridge tower in the world.
At 270 meters above the tarn, the road deck was almost twice the height of the previous
European record holders.
Critics of the project had said that the technical difficulties would be insurmountable, and
the whole scheme was doomed to fail.
They were proved very wrong.
Others said that tourists would avoid the bridge rather than pay the toll fee, the project
would never break even, and toll income would never amortize the initial investment, and
the contract would have to be supported by subsidies.
They would be proved wrong the following summer.
The Minot Viaduct was an instant success, and at the height of the tourist season, carried
more than 60,000 vehicles per day.
At €8.30 per vehicle, the viaduct would pay for itself in less than three years.
So I really hope you found this video interesting, if you did please do hit that thumbs up button
below, don't forget to subscribe, and as always, thank you for watching.