Behind the scenes. Building bridge 5, using I-Girders to span 4 9 metres at O Mahurangi Penlink.

Hightech Road Bridge
24 followers
18 Video Views·Nov 8, 2025
Construction is moving at pace for a new bridge on Duck Creek Road, part of the O Mahurangi Penlink project in north Auckland.
Hi I'm Mike Ryan, I'm the bridge manager here at Bridge 5 on the Omaharangi Penlink project.
It's a seven kilometre road with six bridges. This one's Bridge 5, it's called the Waiti River Bridge.
Bridge 5 is 49 metre span, one lane each way with a shared user path. It's constructed with
head precast girders. It's going to be the longest single span concrete bridge in New Zealand at a 49
metre span. Once the bridge is complete we will cut underneath the bridge another 15 metres,
so it's a top-down construction method. These girders were cast in Te Puke at head precast.
They're 2.2 metres tall. They're able to span a greater span than a traditional super T beam.
We're bringing them into sight in two sections, one 31 metre beam, one 16 and a half metre beam.
We land them and we stitch them together and then there's two rounds of post-tensioning
to pick them up off the bridge. We've used hip transport to transport the girders to sight.
The longer beams have come in on jinkers up the windy Duck Creek Road. The bridge was specifically designed
for this road so that we were restricted to a 31 metre beam length due to the tight nature
of Duck Creek Road. We've successfully turned the girders on site and enabled the girders to be
lifted off at 6.7% which matches the grade of the bridge that we are landing them at.
It's quite a critical bit of detail there to ensure our rigging is correct.
Once we've finished landing these girders we'll complete five stitch bores to connect the 31 and
the 16 and a half metre beam. Once the stitch is complete and we've got a 49 metre girder, we'll
run tendons through. The top five are seven strand tendons and the bottom two are 19 strand tendons.
We'll bring in Presinet who are a subcontractor and they'll use a multi-strand jack and they'll
pull those tendons tight and as they do that we'll actually lift up the middle of the girders
and produce a beam which is self-supporting through the 49 metre span.