The site preparation for the ground mount solar array started this spring and we finally started making our own power on October 31st. This is a 10.56KW solar panel array and I will be making another video in 12 months informing you on the annual solar power produced by the solar panels and a forecast on how long it will take to pay the system off. #solarpower#solarpowerinstall#solarpanels
[Music]
welcome to the 10 Acre Woods my name is
Mark it is currently April 13th
2024 and it's a beautiful day sun
shining uh good time to start on our
solar project uh so my wife Tara and
daughter Tiana are down there right now
uh we're going to be putting the solar
array it's a 10.5 kilowatt uh and it's
going to be going along the side of that
building up into about where this tree
is right here uh so there's a bunch of
trees in here some of these really tall
ones up here are pretty dead uh and
they're within Striking Distance of the
site uh so I'm going to go out and uh
start on that last uh last summer we had
a company come out called prairie house
to do an energy audit uh so the energy
audit consists of going around and
looking at a number of different things
in the uh in inside the house the
insulation the windows uh how airtight
the house is uh and solar is a part of
that so I was looking to get a
government grant uh there is one for
Manitoba here efficiency Manitoba and
then there is what's called The Greener
homes Grant which is the Federal grant
uh so to get in on that I needed to have
this evaluation done uh and uh it looks
like when the house was built in 2008
they didn't put enough insulation in the
Attic r28 uh the standard is R50 here in
Manitoba uh so the energy audit goes
through and gives you what your current
status is and Compares it to a new home
uh and what is expected in a new home uh
and it kind of looks like uh there's an
energy guide that's on a lot of
appliances that say how efficient the uh
the appliance is uh and this is an
energy audit that tells you how
efficient your home is uh so we're
hoping to um cut our utility bill down
uh theoretically
34% of our usage should be covered by
this 10.5 KW system so that's it now uh
I better get out there and help the
girls and the next stage will be um I
believe installation of the piles for
the array
[Music]
[Music]
it's now September 2nd so 2 months later
uh there has been a couple things that
we've had to work out since the uh poles
went in during the installation uh so
you can see those went in and are now
ready for the framing for the panels uh
but one thing that came up is our power
company Manitoba Hydro uh had some
issues with our meter uh and its
location excuse me guys it's uh is it
dinner time getting
close yeah I know
pety so here is our our hydrometer right
here so it's been here for uh about 20
years now and uh they don't like it in
with the animals uh everything's
shielded uh the power's shielded uh they
haven't done anything to the pole uh but
uh they prefer that it be away from the
animals uh so what we had done is we had
installed a new pole here uh we've had
to close off this area this is where our
chickens were uh we're going to change
things up a little bit uh but they
wanted the pole in an area with no
animals uh so what we're going to do is
uh We've installed the pole we're then
going to trench from this pole around to
that one we have to go down two and a
half feet uh to get down far enough so
that they can lay the uh the new
electrical wire and connect it to that
one uh which then runs off underground
to the house so we've held off on
digging the trench just so we can get a
date uh rather than leaving a an open
trench here around with the animals uh
so we do have some dates tomorrow on
September 3rd uh the installation will
start with the racking and the panels so
that's supposed to take 2 days and then
there is a um scheduled booking for I
believe it's
September 12th and 13th yeah 12th and
13th is the next one uh so that'll all
be installed I'm not sure when they're
going to be running the wire through
they might do it all that one day uh but
this splice is going to happen then so
Hydro is going to have to go out to the
pole which is just out there and they'll
have to disconnect it and then of course
they'll have to uh disconnect up here uh
and then bring it over this is the uh
Solar Company is going to do this once
Hydro has done their bit uh by shutting
it off and then they'll move it over to
the top of this pole and then the Box
will move over and then Hydro will slide
in the new bir directional meter so that
they can gauge uh when we're we're
producing more power than we're using
then it gets fed back into the grid and
our meter I guess goes backwards or
something like that not quite sure how
that works yet we will find out that in
a couple weeks time so the guys from
Powertech solar are scheduled to be here
tomorrow and I've got a camera all set
up to capture that so we'll do another
time lapse and here it goes
[Music]
[Music]
oh
[Music]
[Applause]
[Music]
[Applause]
ah oh
[Music]
[Music]
[Music]
oh
[Music]
super
[Applause]
[Music]
all Breakers are on we are now
collecting
solar so it's now November 15th uh and
of course as you saw we have uh
everything hooked up now we had a little
bit of a time uh between when it
finished October 30th and they switched
it on to when they put the uh
communication device that goes in the
house that hooks up to our router that
is able to communicate with the
inverters on the solar panels uh and
then give us our data for the app so
that we can see actually what we're
producing it's uh mid November the Sun's
shining today so we're making some power
that's exciting so here are the micro
inverters uh and there's a number of
them I believe there are uh what is it
there's I think four panels hooked up
per inverter and there's two sections to
the inverter so uh there's wires that
run you can see up and along and down
there so there's two wires that come in
that run in through here and they come
into this breaker and this breaker is
array A and B so we've got 25 uh amp
breaker here and a 25 amp breaker here
and they both feed
into this 50 amp breaker here so we have
control to shut down one of the two
arrays or the entire system here now uh
it is my understanding that if there is
a catastrophic
catastrophic issue there is another
breaker at the house we can shut off as
well as one on the panel so um safety
you know there's lots of safety put into
uh put into this system uh so you've got
your main line that runs here to the
house and then runs underneath the
driveway so it runs up and then it runs
over to the main house breaker so if
there's an issue for whatever reason
there's a short there's a fire on the
solar array who knows um this is your
main breaker to shut off to the house
then of course this runs back
up and it comes
over and into the
house right there so the breaker panel
is on the other side of this wall in the
basement um
they did something
here so I was looking at this and they
took this putty and put it in it looks
like they tried to drill some holes to
go directly in here but our basement is
what's called ICF insulated concrete
forms so it's not a standard wood frame
here this is a concrete slab in between
essentially two pieces of Styrofoam uh
with rebar
so yeah the communication here wasn't
great we could have told them this if
they had come out with the plan so there
was a few issues uh that we had with
them and the biggest one was
communication so then they realized oh I
guess all the wiring is all going
through up here I guess that's probably
where it should go so the other issue we
had with this panel here this was not
the original location uh that they uh
that they were installing it and again
it comes down to communication um so it
was a little bit of a a weak point in
the communication on them uh they
originally installed it here there are
uh screw holes here that it was mounted
and then they just put the screws back
in so the issue we had was of course if
we walk
over to our
stairs and this is our main entry point
here uh there was this
the big breaker sitting right here in
the middle of a nicely finished wall so
we said no you need to put it in another
it's got to be in an accessible area
which I completely understand but not in
the middle of the wall so um so if
you're getting solar installed make sure
that you do a walk through um and get
everything figured out I wasn't here but
terara was so maybe you know maybe I
should have taken the day off um um but
uh really oversee and find out uh from
this video you now know what to expect
and what goes into the system it may
vary in different areas but here of
course you can see the system and uh
there's lots of shut offs so just make
sure you're talking to the contractors
and saying okay where is the main shut
off being put on the house talk to them
about that come up with a solution where
are you going into the house oh yeah you
can't go in there you've got to go in
through here uh so just a few little
things that well hello turbo how are you
today oh looking your
lips done with breakfast
yeah okay so a little change that we've
noticed is well the meter's gone but uh
the wiring is still there so my initial
thought on this was Hydro Manitoba Hydro
did not like that the
even though it was in a PVC Chase
conduit that they didn't like that so my
understanding was the splice was
actually going to be in ground so I was
surprised to see and I don't quite
understand the thinking behind this um
yes there was a meter
there but uh they didn't like the meter
there so they put a splice into this box
um so yeah I'm a little confused with
that but it is what it is
so the original one comes up into here
then they spliced it in and went down
and of course dug the hole through and
over to the meter location on the new
pole Piper are you just enjoying the
sun yeah he's just standing there
motionless well there's it's going to
get cold uh next week the weather's
changing yeah we're going to be closing
the animals in
shortly so uh that will be uh the coming
of winter okay here we go so the meter
will go uh through a series of
numbers okay so we can see that we've
got square square arrow and that is to
the left that means we are actually
sending power to the grid so that's
exciting if it goes block block arrow to
the right it means we're receiving power
from the
grid uh now if we look at the numbers
here delivered so delivered from Hydro
Manitoba Hydro 922 KW since it was
installed on the 30th and they have
received 79 Kow from
us oh boy what's going on over
there so uh there's all the numbers then
it Cycles through uh those readings
so what I'm going to end up doing
because the app that I have uh doesn't
show the power that I've used in the
house uh just the Overflow so this meter
will actually show the Overflow uh what
we've received from the grid and what
we've sent to the grid and that's it but
I have what I'm producing off the app uh
so the app is pretty easy to install and
understand uh I've got it here on my
phone uh and you can see I am producing
n sorry
5.91 KW of power currently uh and you
know the sun is a little low on the
horizon uh in the summertime with its uh
when its angle is a lot better um I can
get uh theoretically up to 10.56 now of
course that's theoretical not actual uh
5.91 that I'm getting now is currently
the highest that I've had uh so you go
in and you've got a few different things
things this is um for the day on what
I've produced uh so 7:30 this morning
the sun came out and I started producing
power and you can see the change there
on that uh on that chart and then you go
into what each panel is producing so
each panel I'm getting uh 352 Watts out
of that one 355 Watts uh these panels
are 480 again theoretical uh 480 watt
panels uh so you can see they're all
producing nicely uh and then we've got
just another screen that talks about our
plant details rooster going off in the
background here had to get away from
that loud
rooster couldn't couldn't think right uh
anyway the um the pre-inspection so I
did talk about the pre- energy audit
inspection that took place uh back in
the spring so we had to finish off our
what's called Greener homes Grant which
is the federal program uh then we have
the efficiency Manitoba which is the
provincial program so I should be
getting about $10,000 back 5,000 from
each of those plus I believe they're
giving me another $250
$250 for the attic instulation that I
topped up from r28 to
R50 uh and then they give you I think
$750 for the PO the pre and the post
inspection uh to cover that so I should
be getting that in they say 40 days 60
days 40 days I don't know in a couple
months it's a it is a government program
so who knows but I'll get that money
coming in to offset so the total price
paid for the
system not including the extra work that
I had to do for Manitoba Hydro to get
the meter moved uh the total amount was
around
$32,000 Canadian of course uh with the
rebates I'm getting you know down 22,000
plus say another 100 bucks so the system
$21,000 Canadian for a
10.56 KW system which I did get a couple
quotes on and this one seemed to be the
best uh bang for my buck the post
retrofit inspection that was done last
week and it was interesting to compare
the pre-inspection with the PO
inspection so of course I'll put
something up right here and you'll see
this is the
pre-inspection uh I believe it says that
a standard house is
117 kles annually is what a standard
home like mine would use annually uh I
believe I was showing 124 K so I was a
little bit higher my house is 16 years
old okay can understand that uh but then
I got the post inspection and I believe
that one was 74 K per per annual so I'm
better than a standard house which is of
course what I was going for uh now one
thing I didn't do is I didn't do the
heat pump system I'm still looking into
that I would like to get a heat pump
system to offset my electric furnace
uh and my savings there I believe was
about 40 K annually uh I have that in
the report uh so heat pump systems are
much better efficiency than just a
standard um electric uh furnace and of
course I'm out in a rural area and we
don't have natural gas here but of
course natural gas uh on that report
again you'll see that I believe the
carbon footprint was at
0.1 uh so it is extremely low because we
are running electric and here in
Manitoba Manitoba Hydro Hydro meaning
water uh Manitoba Hydro generates its
power primarily from water and from dams
so there is a very small amount I think
the number is roughly around 98 90 98
half% uh renewable energy so uh Manitoba
is great for that we've got lots of
water uh producing and exporting a lot
of power So speaking of power we pay
roughly 95 cents a kilowatt hour uh so
that's what's coming in from the grid
that's what we get charged we don't get
that money back when sending it back to
the grid I believe in its early days
that's the way the system worked uh but
you know they uh they changed it for
whatever reason needed some more uh some
more money for infrastructure who knows
uh but I believe the number is about 52
cents a kilowatt a kilowatt hour sending
back to the grid that's what we get so
ideally you know you want to make hay
when the sun shines so to speak um my
wife Tara she was talking about uh well
I'll just do the laundry on a nice sunny
day you can see from the meter we are
sending power back to the grid so we've
we're producing in excess is what we're
actually using currently of course the
temperature is fairly mild I believe
it's about 8° C uh but it's soon going
to be well into the negative digits uh
in the next week or two so um we may not
be sending too much back to the grid
unless it's a sunny day and the furnace
has done its Heating and is then shut
off so I think we will stend send stuff
back to the grid but in a June June July
August in around the midsummer months we
should have uh I should have a credit on
our bill so that's exciting to see as
well and that's something we will cover
12 months from now uh in the uh update
video so that is it I hope you enjoyed
uh seeing the installation from the
beginning right to the end of this
system if you have any question
questions please put it down in the uh
in the comment section we have learned
quite a bit from this process we know a
lot more now than we did when it all
started and if you need uh any
information at all please let us know
[Music]