welcome to the second lecture on the
components of product life cycle
management we are discussing the product
life cycle Management in the course
carbon accounting and sustainable
designs for product life ccle management
I am Dr randip Singh product data
management is the component that I'll
discuss first in today's lecture we
talked about the different components
product data management manufacturing
Process Management change management
supplier management overall managed by
the project management system and we
also saw the different stakeholders
there customers people business strategy
they all participate in the overall PLM
system now when we talk about product
data management definitely there would
be a
database database means it has
information about the customers the
previous experiences the vendors so many
entities are there for which it has the
information throughout the product
design process product data management
is a process that stores and retrieve
information
and this is
done storing retrieving
information to ensure that the details
remains con
consistent throughout the life
cycle I'm putting PLC through the
product life cycle so using the
simultaneous engineering that is the
conc engineering is one of the advantes
when it is required as it follows the
immediate dissemination of information
to those who require it while also
maintaining a control over it so that is
why a database is there which has the
information about the different
stakeholder different entities which are
participating in the product definitely
one of the
major data that you get in the beginning
is the cad data I would call
it
product design or I will call
it CAD
computer dat
design so I have here my product data
management it
interacts the database it get gets the
information from database it keeps on
giving the feedback and also there is
iterations of the design designs would
keep on changing as in when it goes
through certain steps when it goes to
the designer it goes to the engineer it
goes to the final user for use certain
designs would keep on coming so we have
here the product
structure we have the V visualization
because we're talking about the
cad the rendering rendering means you
can look at your product being kept on
your own table you can look at the car
being parked in your own parking space
in your house itself the visualization
otherwise the features of the car the
different curves different colors that
you wish to see all would be part of it
then definitely because we are checking
in and check checking out I will say
this
is check in the data and this is
checking out the
data right data in data out or a
feedback out that means you are having
different
revisions when we have revisions in the
database in the overall data management
definitely we'll have to have a control
and after revisions and control finally
we always have to have
approvals so this has to
communicate this whole system product
data management system has to
communicate with our overall
product life cycle management
system and because we are talking about
the product structure we're talking
about visualization different component
would be there vendors always have to be
part of it so that means sourcing the
information or sourcing or procuring the
component or procuring the materials
that is also important I will put it as
the
procurement
or sourcing this will be more discussed
by Dr pral Pratap Singh in the coming
lectures so how are we connecting this
or are we making an envelop over
it I'm putting it like this this
connection has to be made
here and also enterprise resource
planning which is a complete Enterprise
planning that includes human resource
funding all these parts will also give
an input or the information here as well
the people who are responsible for
policym the people who are responsible
for financing the product and everything
so this is how it goes so this will be
more discussed in the forthcoming
lectures this is just an introduction
next is manufacturing Process Management
once the design is ready once the
database is there second component is
manufacturing process when we talk about
manufacturing process I'll talk about
this in detail when I talk about
manufacturing process as I said there
are softwares which try to manage your
overall product manufacturing that is uh
sens examples if I see uh NX is a
component that talks about the product
design that gives you visualization that
gives you the simulation result as well
what will be the uh performance of the
product in the specific environments
also then in manufacturing Process
Management also we have U the process of
manufacturing process of manufacturing
means the layout the span between
machines Material Handling on those
parts so this is managing the process of
manufacturing so if I put it
here
my
manufacturing Process
Management it involves application
of Enterprise business process and
management tools to the management of
manufacturing management of supply chain
activities within the system or across
the comprehensive
Enterprises I would say
here within the
system
and
across so manufacturing Process
Management
integrates
the E bill of material that is
engineering bill of materials that is
Bill of materal materials of your
product that you wish to manufacture and
the MV of materials that is
manufacturing bill of material or we
also call it as Bill of processes which
are required when we try to structure or
completely manage your product using
the given ebo that means as we already
have the product design here now we need
to have a process design
a process
design and this process
design would always have a process
plan in which we will have our
manufacturing bill of material you call
or Bill of machines whatever you call
this is also known as
bill of
processes
right then the materials being used in
processes the tools the fixtures the
consumables
everything that is processed
material this processed
material is part of it
and Manufacturing process instructions
as it was also mentioned in the previous
slides
manufacturing
process
instructions that is the sheats that we
give to the people who are going to
develop the product the for instance if
it is a software life cycle management
if it is a service life cycle management
if it is a application life cycle
management the complete pipeline the
responsibilities which are given to the
different people people who are going to
design the user interface people who are
going to design the GUI but that is the
calculations which are happening behind
so all the people are given the process
instructions so this is a manufacturing
process in those case those would be the
service process instructions so here
definitely other than the regular
process material will also have to have
the many other resources such as
tooling tooling you can put it in the
process material or you can put it here
in the other resources as well then we
have to have the information about the
governance
models I'm talking about governance here
because we are talking about the carbon
accounting
the
emissions
restrictions all the documents are there
or I can put it here as the
standards these all become
our resources when we're talking about
manufacturing so I'll put this into an
envelope
major one of the most important
component is change management because
change is something that is Rule of
Nature and it is an unchangeable rule of
nature so change request has to be given
change process has to be taken so I will
draw two stakeholder systems here one is
a person who request the change I will
call
him change
requester now it depends whether the
change is internal or change is external
change in internal means within your
factory within your room itself the
change is there within your machine
system small changes there that the
worker or the operator itself could do
or the operator has to only refer to the
supervisor to make small change if the
change is external from your department
the change is going to other department
that also becomes external another level
of external is a change in the material
change in the manufacturing system
overall that goes outside your factory
outside your unit where you're trying to
develop your system that is external
change so it could be
I would say either internal or
external internal
or external here only the things which
are discussed previously like whether it
is engineering change
request or it is engineering change
notice or it is engineering change order
depending upon the level of the change
whether it is within the system or
across the systems or in the system of
the systems it is going out of your
overall system of the systems so it
depends upon the level or the size of
the change that is going to happen so
this external is generally given by
Eco this could be by ECR or
ecn request and notice external is an
order but order is not given by the
change requestor ecoo definitely would
be given by the process engineer the
person who approves the change that will
come here I will put it in between so
now here is a process
engineer process Engineers who try to
understand the quality of your
product or who tries to understand and
the
non-conformance that means he
does testing or
inspection it could be test engineering
manager it could be production
supervisor it could be your uh EHS
manager or if it is external it could be
even your plier
now here we
draw the boundaries and let us put the
process in between what does a change
requestor does he draft the change
request and attach a problem Report with
it then after approval
once the change request is approved by
the first level he
creates
either
ecn or
EC majorly Eco would be created then
Reviewer is chosen between the process
engineer the supplier the manager
whosoever will work here we choose the
rwer or we say
I
select the
reviewer
and EO is sent for
approval once this approval goes here so
I would
say review and
approve engineering change order that
is the responsibility of the process
engineer the supplier or the manager or
the supervisor whosoever is the person
working
in this
manner now we have to implement
the change or the change
order right now once the change is
implemented we now know the change is
there the material which was selected is
not accepted by the people who are
working on it the machine is not able to
do that specific work or the coding
which is given to the specific person
the person is not capable to do that or
we do not have the license available for
the software where this coding is
required or maybe some rendering in the
visualization is not happening that has
to be taken care by having a help of the
third party now this change order has to
be taken is implemented I have said we
have to put the timeline by what time
would you do it so we try to put here
the effective
date timeline is set that is I try to
put
the effective
date this date is put for what that is
today maybe it is 15th of August I have
implemented this change I give you two
weeks now 15 + 14 by 29th of August the
change would be reviewed once again and
that should be reflected to be corrected
so I would put here this is effective
date for
revision
of
change this is the when we're talking
about the implementation of change the
review and approve is always required
done only implementation would happen
and once the effective date is put there
so there is always because Chang is
there change should not happen time and
again otherwise the systems definitely
are having something on stake
when we doing something time and again
the resources which are incurred in that
the time the money the human resource
everything is incur in that so all those
is going waste the change once in a
while is okay once or twice iterations
are definitely would be there when we
try to have a system that could be
completely having a carbon accounted for
as minimum as possible or as per what is
requires or standards now this should
not happen time and again we need to
have a audit
team so we say audit is happening that
is we
notify the cross functional team
this audit
happens only after the timeline is
set that is the next revision of change
that is happening that could be taken by
the process engineer and along with it a
person from a c functional team a
representative would come who will help
us to have the audit of it so this is
the overall envelop of the change
management and this is very important
component when we are talking about the
components of product fly cycle
management after change management
definitely quality management is always
part of it when we talk about change the
quality I when I'm talking about the
people who are working here I'm talking
about the people here it could be
quality engineer it could be the quality
management maybe the bill of quality
could be prepared where quality
improvement is there where design for
Quality could also be there quality
planning quality execution so that the
change is acceptable
in order to accomplish the desired
objectives in PLM the manufacturing
process and product quality are
independent so I would
say
process
and
quality they
are
interdependent so they also depend upon
reproducibility whether what you are
producing is it
replicable is it
reproducible this is what
determines the quality a PLM system is
implemented by Enterprises to streamline
the product growth process the primary
objective of any manufacturer is to
ensure the integrity of their product
manufacturing and they have to follow
the norms for the sustainable
manufacturing processes that is the
carbon footprint has to be within the
norms and definitely if some carbon
sequestration Could Happen carbon
credits are earned so in order to
grantee that system is having a success
in this quality procedures are to be
well developed it are to be identified
rectified at right time and we have to
maintain the standards I'll talk about
the ESG in the coming
lecture where will see different Norms
which are there and different which
standards which are there which
determines the quality of the
systems now one component I will now
like to
discuss is supplier
management supplier management
all right when we talk about supplier
definitely we need to have a full detail
of the suppliers who are there we need
to have a products we have to have the
updated information of the
vendors suppliers are businesses is that
market product and also offer solutions
to other companies by maintaining their
own products so supplier management is
the process that ensures that a business
obtains a value for money it spends on
its suppliers or with its suppliers on
its materials that they're procuring so
maybe to put it in other words suppliers
helps to overall integrate your supply
chain so they help to
integrate
the supply
chain this is there to
facilitate the supply chain into the PLM
and this enhance its ability the ability
of the overall system to facilitate the
part selection process by providing
manufacturer and vendor information at
an outset of that design face itself so
that is we try to maintain supplier
Parts in our bill of material that is
when I create my bill of material we
take into
account account
for
suppliers in bill of material so as I
said in the previous slides we have our
AML that is
improved
manufacturers list of parts then we have
approved vendors list of
parts so those are put here that is I
put
my approved manufacturer list of parts I
put my approved vendors list of parts
here and finally these two are to be
taken together to develop a material
content material content
declaration which involves our
AML and AVL
information when supplier is there and
these are all taken into account or
maintained with their availability of
the material whatever they have and
Supply details are regularly updated we
have
here supplier audit that is
we
audit
suppliers at periodic
intervals right we audit suppliers with
their different uh performance
parameters maybe
their time to
delivery right their cost of components
their quality of
component their after sales
services that means
their
waranty guarantee anything or this
is supplies audit so these are all
managed by our supplier management
system I'll call it
SM so when we're talking about suppliers
and suppliers are to be managed I talked
about already the ISO standards or the
different uh quality management system
that suppliers should also have when we
are trying to get the materials or the
processes through them
so this all is managed by our project
management as now I have explained the
components of the product like cycle
management system which are managed by
overall product
management so these are to be taken for
the carbon accounting as well so what I
will be covering in the coming lectures
is in carbon Accounting in PLM in the
coming lectures I will try to discuss
about different
challenges
in carbon Accounting in in product life
cycle management for instance there is
uh there could be challenges in
data that is data could be uncertain
data could be not clean data could be
having some Dynamics or so we do not
know then we will talk about the
challenges uh in
the product carbon footprint that is raw
material which are being acquired
manufacturing system which are there
Transportation then recycling disposal
there could be challenges in the
relationships between the supply
chain and the
product these will will discussed then
we will see what methodology
could be followed so that
we account the carbon
footprint so that a proper allocation of
system is
there allocation on a way so that the
energy consumed is minimum so that the
product the inventory that is being kept
is minimum so a lot of things would be
taken care and the correlation between
various points we will
discuss then also we will see that how
do
we
validate our
models once we develop this all would be
covered in the coming weeks where I will
give you the different problems the
challenges in carbon accounting when we
talk uh in the product life cycle
management the sustainable designs how
do we do and the design for environment
part will also be touched then we'll
talk about methodologies different
models will be presented models which
could be implemented which could give
the accounts the allocations the
distribution in the system in such a way
so that the overall carbon footprint for
the product life cycle is optimized then
we'll try to see how do validate our
models and you will also see the models
which are developed uh or which are
available already in the existing
softwares I'll give you small
demonstration or introduction to
different soft system which are
available which helps you to evaluate
your product or your
design this all will be covered in the
coming weeks thank you
[Music]