Salvage Operation Plan for the Francis Scott Key Bridge Response

U.S. Coast Guard
69 followers
The Coast Guard and partner agencies continue their work on the Francis Scott Key Bridge response in Baltimore, Maryland.
Our partners with the @usacehq (Army Corp of Engineers) have created a more detailed look at the Unified Command's Salvage Operations Plan, including efforts to establish a limited access channel, in this updated animation.
Learn more about the Key Bridge Response here:
https://www.keybridgeresponse2024.com/
#USCG #francisscottkeybridge #Bridge #Response #UnifiedCommand
the keybridge response Salvage
operations plan is complex and highly
technical with many challenges above and
below the surface of the water but it
can be understood in three concurrent
priorities first we must clear wreckage
like steel and concrete from the 700t
navigation Channel and as part of that
effort clear a 280t limited access
Channel within its span at a depth of 35
ft this will allow three major car
carriers one-way traffic in and out of
the harbor while this is taking place we
must work to refloat the containers ship
Dolly and move it away from the federal
navigation Channel Once the dolly is out
of the channel the US Army Core of
Engineers and its Partners in the
unified command will continue to clear
the remaining wreckage ensuring the
50-ft Deep Federal navigation Channel
opens back up to two-way vessel traffic
we are committed to undertaking this
work with care and precision as we
restore full service to a port that is
so vital to our nation