Grid Solar Power Plant for a Private House with a capacity of 3150 watts

Семен Кузнецов
75 followers
7 Video Views·Dec 11, 2022
Hello everyone friends In this video I will be assembling an AC and DC clamp
And also put our networked solar power plant into operation
Have a pleasant view Let's start
On this channel you will find more than 180 episodes about building a small permanent house with a summer terrace
I installed the panel mounts in previous episodes
Installed the network inverter secured and grounded the HEVEL solar module array
Now we need to assemble two shields One for AC and the other for DC
First I will mount two panels on the wall next to the inverter
I secure it with standard screws with a washer This is possible with a concrete wall
The large shield is secured I immediately install the fuse holder into it
It is used to protect equipment from overloads and short circuits in DC circuits
A 13-ampere DC circuit breaker is connected to the holder
And behind the switch is a surge arrester that will protect our inverter
I am continuing the installation of the AC small shield
I also immediately install two circuit breakers
One rated at 40 amps This circuit breaker will completely shut off power to our entire house
Second 25 amp for on-off inverter
And the third and final block is the AC ultrasound
He will also protect our inverter in the AC circuit from sudden dangerous voltage spikes
Two wires from the solar panels will connect to the top part of the fuse
Plus and Minus Circuit Breaker They will come from below and approach the circuit breaker from above
The wires from the bottom of the switch will go to the inverter's DC bus positive and negative
We will connect the surge arrester in parallel to the circuit breaker and ground it to the earth bus
I am starting to connect the DC panel
Watch the slot machines carefully On one Plus it might be on the left and on another on the right
Be sure to pay attention to this
The grounding wire is to be made separate one rail
The wiring is slowly moving
I connect the grounding wire from the inverter to the ground busbar in the panel
Connecting the main grounding wire
Those interested in how the grounding was done will find a link in the description
I don't have special pliers for crimping the connector but I do have a special hammer
It's well done as far as I'm concerned
I tested the grounding myself using a makeshift method I found online
I don't know if it's working or not but the light is on
I don't have any special equipment for measuring resistance
There is a multimeter for 500 rubles Maybe you can measure with it Who knows
Connecting the inverter to the circuit breaker using a 4 square solar cable
I crimp the MC4 connectors first
I do everything according to the instructions
I remove the covers and connect the
wires + to + and - to - don't mix them up
We just need to connect the panels but that will be a bit later
We continue the wiring
Now we switch to alternating current
Let's connect our inverter to the alternating current
Use 6 square cables throughout the wiring
To connect the inverter to the AC power grid
Using a special adapter that comes with the inverter
The adapter has labels indicating where to connect the phase neutral and ground
Work carefully and without rushing
We connect the adapter to the inverter with a click
Now I send the phase and neutral to the small panel and connect them to the 25 A circuit breaker
And I connect the grounding to the ground bus
AC power cables pass through the back wall
of the DC panel I hope that's acceptable
I would like there to be as few wires as possible visible in the end
The inverter is connected to the AC circuit
I will immediately ground the AC zip
The most interesting part began
I cut a two-core cable to 6 square millimeters and connect it to a 40 A circuit breaker
First I will connect one wire from the house below
Copper conductors with a cross-section of 6 square millimeters are quite stiff
For easier connection I'll take the time for one circuit breaker and a zip
I use pliers to make loops for increasing contact when clamping the automatic
I am placing the circuit breakers back in their place
The blue wire you see is the array grounding wire of the HEVL panel
I mentioned this in the previous series
Now we need to make a parallel connection on the circuit breaker and the zip from above
I am doing this using sleeves and soft wire on 6 squares
I made a loop in the phase wire
A current sensor will be installed on this loop
This sensor will prevent excess energy from being sent to the grid
We will connect this sensor to the inverter later
Let's continue working
The third wire in the middle of the harness which you can see is the generator wire
Phase I0 runs from the pole to this switch
And here is the house
I can turn off the house with this switch
And regardless of whether it is on or off the I0 phase will always be going to the inverter
But this switch I use to turn the inverter on or off
This is already our ultrasound of the lightning arrester
Or something like that In short the lightning arrester
Okay we'll now try to turn it on
The panels are one could say wrapped and assembled
Connect the solar cable to the DC fuse
Then to the array panel
Be very careful as I have already said many times plus to plus and minus to minus
Better check ten times you won't regret it
The switch is in the off position meaning that the direct current from the panel is not reaching the inverter
The panels are connected now let's connect the Wi-Fi module to the inverter
We unscrew two screws remove the cover and insert the module
Thanks to this module you will be able to monitor the inverter through your phone or computer even on a new land
Nothing is being received here at all
The Wi-Fi module was installed it's time to install the current sensor
Connect the sensor to the inverter on the network bus according to the picture in the manual
Great everything is ready for the first start-up
Before turning it on we must measure the current
He should not exceed the maximum current on the inverter in our case no more than 550 volts
Measure to the maximum distance you can start
First direct current is obtained then alternating current
It's kind of scary of course
Now we need to wait 10-20 seconds
If everything is normal it should turn on
The countdown will begin as everything proceeds as planned
He's doing a diagnosis
Power will show how much it is generating now if everything is normal
This is a countdown 60 seconds of diagnostics
It is checking everything
Normal so it's working
270 watts 300 watts gains power
450 watts half a kilowatt 600
There's no sun
I don't know he's also making a lot of noise
Almost a kilowatt
The weather here is cloudy
How much is there already
Already 1.4 kg
It is now necessary to limit the power
Today is today how much did he produce
Total is total
Grid is a network
224 volts 5.4 amperes
Grid 50 hertz
This is PV1 these panels provide 376 volts 3.2 amp load
Power
It produces 1.17 kg
After successfully enabling it I immediately set the
Russian language set the time and date and limited the curre
To prevent the inverter from feeding excess power back into the grid
The grid-connected solar power plant from Volta Energy has been launched
She has already been working for more than a month
In the next episode I will talk about the amount of energy produced
How difficult or easy it is to take care of her and whether it's even worth doing
I'll talk about the nuances that need to be worked on
I will also show how the current sensor works in a visual way and much more
Thank you for taking the time to watch this video
It was interesting subscribe to the channel
Wish everyone good luck see you soon
Goodbye everyone
The sun is now slightly out and is already producing 2 kW
He's been running for about 5 minutes and has already generated 179 watts
I installed a water heater there and turned on the boiler
2 kW
The weather
Of course yes the sun is coming out from behind the clouds
The sun is certainly dazzling
Here you go please 7 degrees
Wow