How Much I've Spent TOTAL COST so far.... - Building a SHIPPING CONTAINER Home.

Earn, Invest, Reap
57 followers
5 Video Views·Nov 8, 2022
How Much I've Spent TOTAL COST so far.... - Building a SHIPPING CONTAINER Home.
Yo! Welcome back to Containing Luxury. On this video,
Dandy's going to be intruding on the intro. What are we actually filming today?
On this video, we're going to be discussing what I've spent so far on our two-container
house build, which is really a three-container house build, but we'll explain that better.
Let's get started.
Okay, so we're going to be discussing what I've actually spent so far on the 40-foot,
the two 40-foot main house, and then the single 40-foot guest house, and we'll show you a bunch
of the designs of what that really entails, but overall, it's 600 and, oh sorry, 960 square total,
wow, leg notes speak good. It is 960 total square feet of indoor living space. However, we have a
covered carport that's probably another thousand square feet, and we have a rooftop deck, which is
another 640 square feet. So if you added everything together of covered or outdoor living space,
we're really somewhere in the 2500 square foot range. So take that into consideration when we're
really discussing we only have under a thousand square feet of interior square footage or under
air conditioning, that we do have quite a bit of other covered space and outdoor space. So with
that into consideration, let's get to the hard numbers. Before we ever even got started, we were
on a pretty big slope, so I had to spend some money doing some grading work. Now I own a Bobcat,
and I was able to truck a subcontract directly to the trucking company, so keep that in mind that
some of these figures are obviously going to be lower because I own and or operate a lot of the
equipment we're using. So with all the lot grading, I still spent $6,500 just on road base to kind of
build up the pad where we were going to be constructing the house. Now in hindsight, I
could have probably done a couple things differently, maybe save some money, but I still have
some money I need to spend in that category. So realistically, I'm expecting that to go up to about
$8,000 by the time I'm done with that. For the three used containers, self-delivered. I own the
trailer, I went and picked them up, delivered them myself. I spent $2,800 per 40-foot container.
They're all high cubes. That totaled out to $8,400. For the foundation work, we again in-house
everything. However, I did need to rent an auger, a rock auger, a Bobcat attachment that drilled the
holes because we're building on pretty much solid rock out there. And for the concrete work and the
forms that we required, pretty much everything, even the, we put rebar in there in the concrete
forms. So it came out to about $1,600. The equipment, which I was just saying, we needed
to rent a lull, a big 10,000 pound lull that was able to actually crane the 40-foot containers
into place. And also the Bobcat attachment, I spent $2,800 in rental fees. And that was just
for one day. So this equipment is not cheap. So you want to make sure you plan everything very
strategically. Now, welding work. Now this was, this is an all-encompassing scope of work and it
was very hard to track what I actually spent as far as that section was concerned because we have
a massive carport roofing structure. We have a lot of welding that was involved and we made all the
stairs and different structural stuff. We cut off the front doors and turned them into awnings.
So we did a lot of welding on this site, but just in that scope of work directly paid to the welder,
we paid $17,000. Now the metal that we bought, that was just labor paid to the welder. Now we
spent $11,200 just on metal that we spent at Triple S Steel. That actually has gone up since
then. I don't think I've updated this. I think between now with the roofing panels and everything,
I should be a little bit closer to about $13,200. Framing, we did everything in-house. We framed it
ourselves. I went over that video with you guys. I spent about $700 on that metal framing. But what
I didn't say in that video is I paid labor to guys. So for me, it actually ended up costing
me about $2,250 after the labor and the materials. So that was just the material cost we did in that
framing video. This is actually everything that I paid, even doing some of the work myself.
Now electrical work so far, I've spent $1,500. That's just the miscellaneous parts, wire boxes.
We did all of that electrical, the interior work ourselves. But that section is probably going to
go up quite a bit once I start mounting my service inlets on the outside. But we'll get to that
section because we're doing something a little differently. Plumbing, we spent $5,500 with our
plumber to run. We needed to rent again another machine, saw cut all the way up the hill. Even
though we're going to make this thing off-grid, I have backups to everything. So I'm going to have
sewer lines, water lines, electrical lines all there just in case I need to connect to them
and want to make my life simpler because sometimes off-grid can be a little bit of a pain.
Next section, drywall. I spent $2,500 in drywall for labor and materials into just
hanging the container. On finishing, I'm expecting to spend about $2,500 as well
into finishing. But I've yet to get that number dialed in and I'm waiting for a subcontractor
to get me that number. But I do enough of this that I would bet that we're going to be probably
somewhere in this $2,500 range. Now, concrete. This was a scope we've already completed and
just the interior of the 40-foot. Again, if you watch our concrete video, it's got polished
concrete floors. We have an entire rooftop concrete deck. Now, I still have concrete patios to pour.
I've got a pad that I need to pour. So just in the rooftop deck and inside on the floors, I've spent
$8,000. So that's going to go up quite a bit more. Flooring. Now, the only unit that I actually
have flooring in is the 40-foot guest house because that's going to be a model for what the
new 40-foot containers that we're going to be mass producing hopefully. That one, we have vinyl
floors that are 100% waterproof and it's going to cost me about, it's 320 square feet at
$2.50 per square foot, came out to $800. That's again, materials only. I'm going to install it.
So that should be fairly accurate as far as what it's going to cost me. I've already picked out
the product. That's about where it is. Windows and doors. We used all storefront glass. If you
watch our window video, that was a major pain, but still it had nothing to do with the cost.
I still paid $20,000 just in windows and doors. Appliances wasn't cheap. I spent
almost $6,000, $5,900 in appliances. We went with the black stainless steel,
that's washing machine, dryer, fridge,
that's it. Oh, stove and microwave. I didn't want a dishwasher. I actually don't even use
my dishwasher in my house. It does a horrible job. And if you've ever done your research,
energy star rated means that they take out the heating element that dries the dishes.
So they always come out soaking wet and that's your energy star. Cabinetry. So I kind of brushed
on this before with you guys, the cabinetry for just the one kitchen on the inside is $10,500.
I ordered some cool matte black custom cabinetry directly from California. Super cool company.
We'll get into them in future videos, but really like the built-ins and the products that they
offer. I think it was actually, believe it or not, even though it sounds like a lot of money,
it's really not that much. We've done condos with similar size kitchens and seen people spend
30 or $40,000 just on the cabinets. So 10,500, it is a lot of money, but we've supplied
the same amount for a lot more money. So countertops, I've yet to get this price
because they're going to need to come in and template. And I don't know what countertops I'm
going to have made, but I'm giving myself an allowance of about $3,500 for all the countertops.
That's a pretty, I'm pretty good at that number because I do a ton of these and I am using a
product I buy a ton of. So I'm using concrete gray quartz. It looks just like concrete. It's
relatively inexpensive for big jumbo slabs and I'm pretty sure I can get it anywhere. So
that I'm expecting to spend about $3,500 for all of my tops being made.
Paint. Paint was actually a sore subject for me because it has been a mess out there. I have a
lot of work that needs to be cleaned, redone, and it's been very expensive. So I've paid $3,800
to a painter and I spent about $4,200 on paint with Sherwin-Williams. In hindsight, I literally
might be going backwards. And I sprayed the last container we built with a Bayer oil base,
just from Home Depot. The product went on super nice. There's no runs and it's been,
I mean, it's been beat up. It traveled across the nation and it's holding up absolutely fine.
I spent all this money on this insane product. You know, it was a pain in the ass,
pain in the butt, bleep out myself. It was a pain for the application, the painter.
I don't know. It was real heavy spots, really thin spots. I used to own a painting company,
so I should have just painted it myself. It would have been a lot smoother of a process and I
wouldn't have nearly as much to go back and fix. But that cost me $3,800 to him and $4,200 in paint,
which is astronomical. I think you should be able to get that entire number down to about $5,000.
Interior. I'm going to spend about $850. I'm going to paint it myself. That's not a... $850
is pretty much all the products I'm going to need. Tape, plastic, roller naps. I'm using a
couple of different products. I'm going to have some stains. I've got some woodwork to do. So
about $850 is what I expect to spend on materials. If you were going to pay somebody to do that,
I would probably talk about $2,000 onto that. Now, keep in mind, if you're mimicking our build,
that would be a number, not for a single 40 foot. Okay. Millwork. Doors and baseboards.
That I'm expecting. I'm, again, giving myself an allowance. I've done some shopping. I have a
pretty good idea of what I'm going to be using. That number might go up, but I gave myself an
allowance of $1,500. If I end up going to these crazy glass door systems that I really like that
just did in a commercial building, I might end up spending quite a bit more than that. But at $1,500,
I have a lot of options and I think I can make that work. I might just build some barn doors
for it, but we'll see. Decking, composite decking. I ordered this. I don't ever want to deal with
restaining or replacing rotted deck boards, any of that stuff. I have trucks decking at my house
here in Florida. It gets beat up by sun all day long. It looks identical to the day I bought it.
So I, again, went with a composite decking. It's really expensive. If you do your research on it,
there's no way around it. So the stairs that I have being made and the treks deck boards,
it's not treks, it's a different company, but it's similar to treks. I spent $3,500 just on
the boards needed to, for the landings and the stairs. That's the only place that that's even
going anywhere, but $3,500. Labor decking, I'm expecting about 750 bucks I'm going to spend
between paying the guys. There's also going to be some miscellaneous stuff in there. Like I'm
going to need some self-tapping screws to drill through the heavy gauge metal that we have out
there. Probably some, I might even have to pre-drill some of it because we have some really
thick stairs. Plumbing again. So my previous number of plumbing for bringing all those lines
up the hill is actually all of my plumbing fixtures on the inside. My shower pan, shower
valve, sinks, faucets, garbage. I'm actually not putting a garbage disposal in, but all my sinks
and my faucets and all that kind of stuff. That came out to about $5,500. Now I have to pay a
plumber to saw cut and do all my roughs, my undergrounds coming up. That's going to be
another $5,000. So my previous one, I misspoke. This one is $5,000 for all the saw cutting and
all that kind of stuff. Now the last and final, this is dependent upon if you're trying to go
off grid, which we are, and I love container houses being off grid. So solar, this number,
I think is actually really low. I've met with Willpower Solar. Once we get to the solar,
I'll put a link to all their info, their company out of San Antonio. Really cool.
We've worked together. We've been trying to design and make the most cost effective off
grid system that we could possibly come up with. I think he's done a fantastic job keeping the
price down and it came out to $17,000 for six kilowatt off grid system. We've got plenty of
battery storage and he made sure to get top of the line. He went through all the reviews and
warranties and tried to get stuff that was made sure it was going to last because there's
definitely cheaper versions of stuff, but we went with some really high end stuff
and he got me 405 watt panels, which are crazy. So anyway, if you totaled up all of those things
that I just went over, we would come out to $152,550. So that's what I'm personally spending
being GC, doing tons of work at the house. That doesn't even cover landscaping, driveway,
sod. I've got landscape lighting. I've got a lot more stuff that I really need to do out
there to get this thing finished. I would realistically think that it's probably going
to end up around $175,000, which when you think about it, it's only a thousand square foot house.
You're talking $175 a square foot for interior living space. That's pretty high. However,
I have floor to ceiling glass. I have custom matte black soft clothes, crazy cabinetry,
I have really high end finishes, glass walls. So when you think about it, that number does
seem very high as far as price per square foot for building a cost effective home. However,
I also have about 1500 square feet of outdoor living space or covered space that I'm using as
a garage or storage area. And also we've used very high end finishes where if you had a builder come
out and build with these types of finishes, your house is not going to even be close to the $200
a square foot range. I think you're looking like California builder style and you're going to be
anywhere else in the country for a high end floor to ceiling glass, that kind of look,
you're probably in the $250 to $300 a square foot. So some people might chime in and be like,
no way, I couldn't even build it for 500 square foot. So I think with the pricing,
it sounds like a lot, the price per square foot breaks down to a lot, but I did some stuff that's
very custom. It's going to look really cool. And I think you guys are going to love it when it's
done, but it still hurts. $175,000 is, you know, it's a lot of money to dump into a dream project.
So with that being said, we hope everyone, you know, again, we're an educational series,
so I'm literally building all this stuff and sharing all this information with you guys.
So, you know, anything you can do to contribute back to our channel,
share our videos, make sure when you subscribe and hit the notification bell,
that's about it. Thanks a lot. We'll catch you guys on the next one. Container luxury out.