How Do Engineers Sink the World's Longest Undersea Tunnel? | Extreme Tunnel Projects

Hightech Road Bridge
22 followers
AI Generated·May contain errors
Video Summary
AI GeneratedThis video examines the engineering complexities of large-scale tunneling, contrasting the construction of the Snowy 2.0 pumped hydro project and the Fehmarn Belt immersed tunnel with various global renovation projects. It highlights the use of Tunnel Boring Machines (TBMs), immersed concrete elements, and adaptive strategies to overcome diverse geological and aquatic challenges.
800 meters inside Australia's snowy mountains
sit caverns big enough to hold the Sydney
Opera House.
Between Denmark and Germany,
an 18-kilometer tunnel sinks under the Fehmarn Belt, and Virginia
bored one beneath its harbor.
Rock keeps changing and water pushes back.
Here's how tunnels push through mountains
and under seas anyway, and see how the sea
tunnel's final piece stretches to close the gap.
In Australia's Snowy Mountains,
crews are digging a hole to store electricity.
Snowy 2.0, the country's biggest pumped hydro project,
could power 3 million homes for a week.
This shaft at Marika drops 246 meters, 1200 tons of rock per meter,
which makes your fence post hole look lazy.
And that's just the entrance.
Building inside a mountain starts
with reading the rock before anyone cuts it.
Geologists drilled 42 kilometers of core samples,
and the machine was set up for hard volcanic stone.
Then the walls changed color and fossils appeared.
Coral? Up in the mountains? Get out of here.
It was a reef that grew around an ocean volcano 430 million years ago,
then shoved skyward by colliding tectonic plates.
Limestone cuts differently from volcanic rock,
so geologists now drill ahead and warn the crew what's coming.
Tantangara.
The machine named Florence started out in friendlier ground.
It bored through sandstone
and siltstone from an ancient seabed 440 million years ago.
Strong but cracked just enough to cut easily,
so it ran in open mode with bare rock right
above its shield. Over two months,
it averaged about 40 millimeters a minute.
A garden snail could pass it,
though the snail isn't leaving an 11-meter tunnel behind.
In the cab, operators watch navigation screens
and a camera on the conveyor belt.
Florence wasn't the first machine
into these mountains. That was Lady Eileen Hudson,
lowered into its launch pit at Lobs Hole by heavy cranes,
then commissioned system by system before it cut anything.
It also got a naming ceremony
with speeches, because apparently you
can't start a tunnel without a few.
Its first tunnel was a 2.85 kilometer access route,
then crews took the machine apart.
At Talbingo, it got a new cutter head, shields
and main drive for the 5.8 kilometer tailrace tunnel.
Meanwhile, Florence hit rough ground,
and people kept asking whether it was stuck.
It wasn't.
It has now passed seven kilometers,
halfway along the headrace tunnel, with planned pauses
for probe drilling and maintenance.
But every two meters it cuts leaves bare rock
behind, and something has to hold that open.
Concrete for the tunnel lining starts in a local quarry.
Local quarries have supplied a million tons,
including basalt crushed into aggregate, the
The stony part of concrete.
Batch plants sit at four sites
because concrete starts curing within about two hours.
Ship it too far and you're delivering a boulder.
Crews use more than 20 mixes for precast segments,
concrete sprayed onto rock,
and concrete poured in place for intakes in the power station.
Every mix is tested before and after mixing
because the target is 150 years.
Inside the Polo Flat factory, robots handle the repetitive work.
Robotic arms pull finished segments from their molds,
clean each mold and spray on a release
agent, the factory version of greasing a cake pan so nothing sticks.
These robots clean up after
themselves without being asked,
which already puts them ahead of most teenagers. Telehandlers
carry rebar cages into position,
cranes lift fresh segments out, and the storage yard fills
row after row. Every piece is headed
for 27 kilometers of tunnel lining.
Deep in the mountain, those segments finally meet the machine.
Lady Eileen Hudson's cutterhead is
11 meters across, and the full rig stretches 137 meters,
with up to 18 people aboard,
working around the clock.
Segments ride in on a service vehicle, then a vacuum erector grips each
piece and sets nine of them into a ring.
It's a giant suction cup, basically your car's phone
mount with a lot more riding on it.
Grout then fills the gap between the ring and the rock.
Underground, precast rings, line the round tunnels,
and sprayed concrete covers the rest.
The main access tunnel is lined with almost 13,000 segments.
Cross passages were blasted,
then held up with rock bolts and shotcrete.
Concrete sprayed onto rock.
One batch plant makes 100 cubic meters an hour.
Rock rides out on conveyors while segments and concrete roll in.
Running a tunnel is basically
a delivery business with a drill attached.
The power station...
Though, needs caverns too wide for any round machine.
Getting crews and gear to the caverns took a better road first.
The 15-kilometer ravine road into Lobs Hole was widened
and paved for all weather access for about 2,200 workers.
When your commute drops into a mountain ravine,
fresh asphalt counts as safety equipment.
From the main access tunnel,
smaller drill and blast tunnels branch off toward the power station
complex. Another tunnel machine, Kirsten,
boring the emergency cable and ventilation tunnel,
had already reached the complex with only 400 meters left.
Then the caverns started to connect.
Crews dug the machine hall roof
from both ends until three meters of rock remained,
then drilled, charged, and fired it with electronic detonators.
Surveyors and tunnelers, when two headings finally meet,
how far off are they in real life?
Put your honest number below.
Meanwhile, a factory overseas was building parts for that hall,
like draft tube liners 30 meters long
and generator frames weighing 270 tons each.
Measure twice.
Cut once hits different when the cut is a cavern.
Today, 800 meters underground,
the power station caverns are big enough to hold the Sydney Opera
House. Holy cow, a whole opera house of empty space inside a mountain.
Crews have fired about 3,000 blasts,
working down in benches 6.1 meters deep.
Each round means drilling, charging, blasting, hauling out broken rock,
scaling off anything loose, then rock bolts and shotcrete.
The total dig comes to 1.4 million cubic meters.
Room for the machines? Sure.
But can it handle the water rushing through them?
The water gets its own plumbing, and it is huge.
Behind the machine hall, three waterway tunnels
hold collector pipes, steel tubes 266 meters long
and six meters wide that carry water away
after it spins six pump turbines rated at 2200 megawatts.
Near full capacity, they'll move enough
to fill 40 Olympic pools a minute.
Your garden hose would need about five years
to match one minute of that.
The pipe sections sit on temporary steel supports for welding,
then get buried in concrete.
Uphill sits the steepest piece, the inclined pressure shaft.
It climbs 1.6 kilometers at a 47% slope, so Kirsten was rebuilt
with platforms that pivot level and walkways that turn into stairs.
Leg day comes free with every shift, but when the turbines stop,
where does all that moving water go?
That's why the shaft at Merica exists.
17 kilometers of 10-meter tunnel hold about 650
Olympic pools of water, all moving at once.
Oh my gosh, that's 650 pools hitting a closed gate.
Instead, it surges up the shaft,
like the bang in an old house's pipes at mountain size.
At the upper end, Tantangara, the water first enters the system.
A diffuser smooths the flow
toward the gate shaft, while trash racks catch logs
and storm debris before they reach the tunnel.
Trash racks are exactly what they sound like,
which is refreshing in an industry run on acronyms.
At Talbingo, the water reaches the lower reservoir.
Here the tunnel shifts between round and rectangular,
and crews poured 560 cubic meters
into one roof section over 10 hours.
Pumping sends everything back uphill. Snowy dug through
rock to move water, and the next project sinks
a whole tunnel into the sea. Between Denmark
and Germany, the world's longest immersed tunnel
is going in without a boring machine.
The Fehmarn Belt crossing gets 89 giant pieces,
cast on land, floated out, and sunk into an
18-kilometer seabed trench.
Prefab construction, except the parts are supposed to sink. First,
crews need a factory, a harbor, and that trench.
On the German side at Puttgarden, the first year
was mostly groundwork.
Crews laid power lines, cables, and water pipes, built two transformer stations
and started three bridges where motorway and railway meet the tunnel.
Offshore, some of the world's biggest dredgers worked around
the clock on the trench, and
barges brought seabed material back to build those bridges.
Topsoil from farm fields was stripped and stored.
The farmers get their dirt back afterward,
which is more than most of us get from a borrowed
ladder.
On the Danish coast, the harbor basin needed
a floating excavator named Simpson.
Its arm reaches more than 20 meters,
and its bucket holds 34 cubic meters.
That's about the size of a kid's bedroom,
and just as hard to keep clean.
Steel teeth tear through stiff glacial till,
carving the work harbor and the channel the tunnel elements will use.
The dug material reinforces dikes around new land.
The harbor walls themselves are built from granite.
Breakwaters and coastal protection at Red
by Haven need more than 2 million tons of the stuff,
around 50,000 tons every week,
dumped from barges by excavator to create Europe's biggest work harbor.
Somewhere, a quarry owner is having a very good year.
By summer 2022, the Danish side had become
the largest construction site in Europe.
The first of three factory halls was up.
The work harbor was nearly done. Housing for more than
1,300 workers was rising, and the trench was over half dug.
Next up, casting tunnel pieces longer
than two Manhattan blocks.
So they built a factory whose only product is tunnel. Between late 2021
and summer 2022, bare dirt at Red by Haven turned
into steel-framed production halls.
Nothing says commitment like a factory with one customer.
Then the steel showed up by sea.
One shipment alone brought 1,800 tons of rebar,
lifted onto trailers at the West Quay.
About three cargo ships dock weekly,
sparing local roads thousands of truck trips.
Production finally started in summer 2023.
A rebar cage slides into formwork
and takes about 3,300 cubic meters of concrete
over roughly 30 hours.
After curing, the 24-meter segment gets pushed forward
so the next can be cast.
Nine segments make one element.
It's an assembly line moving at DMV speed.
Across the water
at Puttgarden,
part of the tunnel is being cast right on land.
Crews pour the floor first, then the walls,
then the roof, with the deepest point 12 meters below sea
level. Not long ago this spot was the Baltic Sea,
so calling it a basement undersells it.
By summer 2023 both coasts were moving at once.
Elements were taking shape in the factory,
the portals were rising, dredgers kept deepening the trench,
and new roads and rail lines stretched
toward each entrance.
But every finished element is a giant concrete box sitting indoors,
and somehow it has to float.
Floating starts with water, and a lot of it. Each element's
ends are sealed with steel bulkheads,
then the basins outside the factory flood.
The first fill took over a million cubic meters,
about 640 Olympic pools.
Here, a floating gate makes its first move,
separating basins while water levels change.
The first element is 217 meters long,
weighs 73,000 tons, and floats.
Air sealed inside its tubes keeps it up the way a ship's hull works.
To sink it later, crews add 4,500 tons of ballast concrete
while pontoon vessels hold it up so it
doesn't sink in the harbor.
Dump trucks and rollers spread the ballast in layers, balanced
side to side. Pile too much on one side
and you've built the world's longest leaning tunnel.
Meanwhile, the German portal got ready for its first element.
Its tubes were sealed with bulkheads, a new dike went up over them,
and in late August 2024, the area between the dikes was flooded.
Then the temporary dike came out,
leaving the portal reaching out into the Baltic Sea.
In May 2026, the first element finally went under.
Tugboats towed it out through the harbor basin.
A special vessel positioned it over the trench,
and crews eased it toward shore before
lowering it gently onto the seabed.
Years of prep, all for a tow slower than a parade float.
The joint between elements is where the animation shows real precision.
Sensors on the seabed and on the previous element guide each new one
into place within 12 millimeters.
A steel beam hooks a U-shaped bracket
and hydraulic arms pull both elements tight.
Pumping out the water trapped between them
lets sea pressure squeeze a rubber gasket
shut. That squeezing comes free.
Maybe the only free thing on this entire project.
A second inner gasket follows,
flexible enough to handle seasonal temperature swings in the water.
Real footage and animation together trace
the route from factory to seabed.
Ten of the 89 elements are special, shorter,
and wider, with technical rooms underneath.
After joining, the trench is backfilled with gravel
and sand and topped with protective stones,
and the current covers it all in sand.
Crews fit out the tunnel from both coasts,
and a final element that extends at both ends closes the gap.
The result? A seven-minute train ride or a ten-minute drive.
Sinking a tunnel works with calm water and a factory on shore.
For a bored tunnel, the production line has to travel with the machine.
The next tunnels ahead include some dug from scratch
and others rebuilt while traffic keeps moving.
A tunnel boring machine starts life as a pile of parts.
In Virginia, a machine named Mary arrived in 170 components
and took roughly six months to assemble with gantry cranes.
Most of us have given up on flat pack furniture with fewer pieces.
Fully built, it measures about 14 meters across and 131 meters long,
boring under Hampton Roads
to create Virginia's first bored road tunnel,
only the third nationwide.
In Switzerland, the Eppenberg Tunnel shows how
a machine adapts mid-route.
The rail line needed two extra tracks with no room through town,
so crews built a bypass tunnel about 3,100 meters long.
Loose ground at the start was dug under
a roof of steel pipes drilled in ahead.
Then a 13-meter machine took over,
building a six-segment ring every two meters.
After 1,800 meters, it hit gravel full of groundwater
and switched to pressurized clay slurry to steady the face.
The machine even dug its own garage for that eight-week makeover.
Afterward, it moved at about a quarter speed.
At Switzerland's Belchen Highway Tunnel,
fixing old tubes meant building a third one first.
The original tubes are 50 years old,
and their rock contains gypsum that swells when wet.
It's rock with a particle board problem.
Get it wet, and it puffs up.
A machine almost 14 meters wide built the new tube
so traffic can shift while the old ones get repaired.
Behind it, crews welded waterproof membranes, tested every seam
with air, and poured the inner concrete lining about 10 meters a day.
At the Petersburg rail tunnel in Germany,
there wasn't space for a new tube. Current rules require
four meters between track centers,
so the existing tunnel had to be widened while trains kept running.
During a four-week closure,
crews set a 470-meter steel and wood protective tunnel inside,
leaving one track open.
Then they blasted the mountain away around that shell.
Each blast needed a track closure and safety check,
then trains resumed every eight minutes.
Imagine remodeling your kitchen while everyone keeps cooking.
Switzerland's Lötschberg Summit Tunnel has carried trains for a century,
and its 1970s track was worn out.
Crews are replacing two 14.5-kilometer stretches
with concrete slab track while trains run next
door. Supplies ride a monorail hung from the tunnel,
lining on anchors tested at double their
load. Each 300-meter stage gets one week,
and the old track comes out in eight hours. About 220
trains rolled past during removal alone,
and the excavators froze for every one. Red light,
green light,
professional edition.
Water pushed through
a mountain to make power.
Traffic crossing beneath the sea,
old tunnels rebuilt around running trains.
All of it ends up hidden.
And that's exactly the point.
When Fehmarnbelt opens,
drivers will cross from Denmark to Germany in about 10 minutes,
18 kilometers under the Baltic, with the sea overhead the whole way.
Some people love that idea.
Others would happily keep taking the ferry.
Thanks.
The tunnel has separate tubes for cars and trains,
a service passage between them,
and ventilation built in,
yet the feeling of being under the sea is hard to switch off.
So be honest, would you drive that tunnel without a second thought,
or grip the wheel until you
see daylight again? Tell me below in the comments.
Thanks for coming underground with us, and
And subscribe so the next deep build reaches you.
See you.