25 steps to design your House | Interior design Construction step by step process | interior Coach

Architectural Course
8 followers
So whenever we are building our own home
So in our group, there's always this confusion going on.
Should we paint first or lay the tiles first?
First, make the false connection; first, do the wiring
So in today's video, I'm going to tell you about 25 steps.
from scratch to handover
Because you've received so many comments
Which you have repeatedly asked me about
Dude, what thing should Manish do first?
So since the first step occurs
Pasting of references and 3D designs or 2D drawings on the wall
I mean, if we are designing it ourselves
Keep relying on your own creativity
So whatever references you choose from the net
You need to print it out for him.
And stick it on that wall.
Or whatever your designer has
We will provide you with 3D designs.
The second step is line marking.
The meaning of line marking has become
Inside your entire house
You need to put a masking tape on the floor.
And if your house is raw
I mean, I didn't take the tile.
So you're talking about the lime powder that is
It comes out very cheap.
Quite a lot can be had for 100-200 rupees
You can mark it yourself.
Step 3 is the protection sheet
Now, those people's homes where
Flooring is already installed
So here you have
A protective sheet needs to be applied to a branded company.
So that your tile or marble
It is a protector, and no matter what type of
without scratching or breaking
Step 4 now comes dismantling
If the goods here are like this
The tiles in the washroom need to be replaced.
The old kitchen needs to be demolished.
Either this wall has to collapse and shift.
So there, you have all the work
First, we need to carry out the demolition.
There are two things to keep in mind here.
First, you need to organize the trolley.
And if you live in apartments
Flowers are there, so you should take a look at this
That all the Malwa should be dumped
And you just need to talk to a contractor.
Because often in apartments you get Malwa
You can't carry them outside; you need bags or
One has to fill the baskets and pour out the spring.
You should have already discussed the rate with your contractor.
It has been phase 1 so far.
Now it's sorted, starting from here, phase 2
So here comes our Step 5
Meaning that the work related to electricity
Here are all the electrical boxes for GI
I mean the boxes that are installed inside the wall
Inside which we mount the switch plate
All those boxes, all his pipes, first of all
We have to deliver it, and after that
The most important one among all those areas
Step 6 is now here; this is what we need to do.
Here is the framing for the fall ceiling
Just need to frame it, nothing else to do.
After step 7, we need to carry out the piping inside that fall ceiling.
And you need to route the wiring.
the reason being because if they do anything later
It will become a mess.
When the wiring is done in the false ceiling framing
So here you have everything.
You must think through the advance option before proceeding.
So, are you planning to install a video doorbell?
So is her wire going to be taken?
Or is there any cable coming for your Tata Sky?
A cable for your Wi-Fi is coming.
As all our wiring has gone inside the ceiling
Now comes step 9: what we need to do
Install AC copper piping
And I also need to get its drain pipe installed.
And then, pull it here.
What's the reason for his photo?
The house is fully ready, sir.
Let's think about the future, buddy
Let's get a painting done here.
So your carpentry electrician, whoever comes,
He lifts a keel and strikes straight into the wall.
And it turned out that your AC's drain pipe is
Leaked now step 10 comes
Our plumbing is first of all your entire
Tile breakage, we have already done, so first will be
Your first coat of waterproofing will be done again
Second coat of waterproofing with fiber mesh netting
We have to pay the tax there after the Khangar filling.
PCC and that's it, the bathroom floor is done
Ready and instantly waterproof
Now comes the most important trick, the one that...
Once the pipeline is complete, you will be
Turn on the water; don't worry, the pipe end will be fine.
Caps are placed to prevent water from leaking out.
Step 11 is now upon us
wall punning, which I often say, brother
If you want to give a luxury home
So the paints that come are Mengi-Mengi Asian Paints
which is running the Royal series, with its 20-liter capacity
The bucket comes, 12-13, the illness comes in the form of a fever.
While normal 2-2.5 occurs in the illness
So, there is no value for paint here
The value of paint's base is compromised if the base is not good.
No matter how much you paint it, it will eventually deteriorate.
So I'll tell Ameya, go for POP
punning and if you're not doing POP punning
Don't use normal putty; use acrylic putty.
What will happen if you let it go? It becomes finished and smooth.
POP punning covered only slightly less
But it will be good, and that too
Only one coat comes to us now
flooring because tiles or stone are coming loose
could have been damaged, after that we
We will apply the skirting, but here you are the one who
The trick is knowing how to maintain the level.
To walk by doing it, take this and always keep walking
If your property is a house, then first of all ground
On the first floor, stone will be laid, then the staircase
Then it will come to the first floor level, then first.
from the floor to your bathroom to the kitchen
What if tomorrow your bathroom is upstairs?
Come here and your bedroom level is down
Always keep this in mind.
Now, the little trick in this is if
Your UPVC frame is being installed, right?
If aluminum windows are being installed
So here you always have a border
Giving a granite stone is just giving a granite stone.
Is it not necessary to lay tiles, or something else?
No, do not add reason why for what
I've already made a video about the bathroom.
I always use flooring for wet areas that are
Shower, you're taking that to the bathroom.
Always 10 mm from normal flooring
Down Lakhna Step 13 of our entire
Tiles have been installed at home, and stones have been laid.
So now, what needs to be applied here again always?
protective sheet so that our flooring doesn't get damaged
You are at step 14. Now, what do you need to do?
Toughened glass for the entire house
What do you need to do in step 15?
You can place an order for your kitchen right here.
No, meaning kitchen wardrobe
TV unit if all of these are in modular factory finish
If you're having it done here, you don't need to place an order here.
Now, what do you need to do here, granite or quartz?
Whatever you want to fix on the kitchen countertop, fix it.
I need to go now, as soon as the kitchen
Like shutters on a wardrobe, ready
They have become very important here now.
It's a trick to reopen all the shutters again.
Yes, and wrap it with bubble wrap.
to any safe and secure place
You must keep it here now, even if you want to. This is your existing one.
Put it in another house, in some room
Have it done, but keep it safe. Step 17
What you need to do is clean your entire house.
lights, wires, switch socket
All purchases are for you, whatever you need
If you like the model, you'll buy it.
Step 18 comes now. Now from here, as ours
switch plate, wiring whatever ours
The job of a minor adjustment in the demolition and reconstruction work
It has already been done; now we just need to do this here.
What needs to be done first here is the first coat of
Square mud, sending, then second
coat of chauk mitti, sending,
first, then primer
coat of paint and then here
You must finish the work and be done with it.
Why close it? Because
The wall that shows us undulations
The undulations are most visible in the lights.
Gives the goods, people, if we have your final coat of
It would have been painted, and the lights installed later.
If undulations become more visible after the light is turned on, then
What should you do after the first coat of paint?
And along with it, when he will be repairing it
Here, all your items will begin to install.
like shower glass partition you have
If you have any UPVC windows
The painting was supposed to be applied; you have already applied the painting.
Yes, if you hammer a nail there, then the painting will be on the wall.
have to take it back again, the reason being that
Later, when the final coat of paint is applied
Then there was a painter there
Any other man
should not be the case, because if there were another man there
So, be firm and say it with your own hand.
If you paint on the wall, it will get damaged, and then
Now comes step 20
Our final coat of paint on our entire
Painted at step 21 at home
Now it's our deep clean, the one we've done deep clean
It's better to hire professionals rather than local labor.
Never do it from now on, step 22
You must perform planet entry.
And here, you are in your own palace.
To get on the bus, step 23
You have to make one.
Snaglist Snaglist means that you are here
You must stay in touch with your contractor.
And until the next Friday, you will have all the things
You have to check using it, whatever thing it may be
Ishu is coming, so inform your contractor.
Next, I wish that Manish would get us a list like this
Then it won't be fun at all, don't worry
I have made a video for this.
The four parts on top of the interiors
That video is in my playlist, consisting of five parts.
In the same playlist, first or second part
Below is a detailed Excel sheet attached
Download it from Google Drive.
And build your house step by step
A palace of dreams
You must have liked the video.