First step: Go get the brick, the concrete, and how to set up the footers for your brick underpinning.
We put a metal skirting around this mobile home so it would pass inspection, we're now removing it so we can put nice brick skirting under it.
Okay, y'all. When you decide you're going to underpin a house, you just go to the brickyard,
get what you want. I'm down here in a company truck so I can haul more, get a load at one time.
I'm about 100 miles from the mobile home and we're trying to get these brick right here,
but if we can't get those, we're going to get those down there. So they're running a special
on those, but I'm switching to those. I'm trying to. So if these are not sold, I'll be,
if these are not sold, I'll get those. If those are already sold, I'm going to get those down there.
So we'll see. Okay, y'all. Just like that, we got bricks here. We got bricks there,
bricks there, bricks there, and bricks on my truck. So we'll be hauling a pile of today
back to the ranch, the farm, wherever, store them. So we need them and we're going to need
them here pretty quickly, but we got them here. We got them secured. We got a hell of a deal on
but we got them in here. We're ready to go. So that's all we needed to do. So yeah,
this was adventure, but we got it. Okay, y'all. This one, we're going to,
everybody's wanting to know how to underpin these, put a foundation under them, put a
skirting. It's called all kinds of different things. That's what we're going to do. This
one's got this metal skirting under it. We're going to put bricks under it. So we're going
to take this skirting off or this foundation or footing or whatever you want to call it.
We're going to take this stuff off. We're going to put brick under it. This is how we do it. This
is not necessarily the way it has to be done by any means, but this is what we do. So we're going
to, we're going to see what we can do here. See if we can get some stuff started. We're pulling this,
this, uh, metal off of here first. This is all for, it's just, um, just to look at.
It is not weight bearing or nothing like that. It's just, uh, it's, uh, what's the word I'm
looking for? Um, cosmetic, just cosmetic. So the bugs are going to be bad today. It looks like,
I'm slapping them away from my face nonstop, but this is what we're, this is what we're working
with. Taking this off. We're going to be digging a footing. We're going to be putting concrete in
the footing, and then we're going to be, um, putting bricks on top of that. I got a little
bit of sand delivered, so we're going to be, uh, seeing what we can do here. We've got concrete
we've got concrete, pile of concrete there, and we've got bricks. So we should have everything
we need to do, and, uh, we'll see what we can do here. We're going to slide these steps back out
of the way. Tell y'all what we're going to do. We're going to set up a, uh, string line from
one side to the other, so we can tell what our height is. Basically get that string line level
across there. We know the trailer's level, so we can measure off that trailer, and we'll know our
string line is level from one side to the other, and then we'll be good. The bottom of that ten
there, we know is level across there, so we can measure from that. That'll get us everything.
The actual footing is these bricks, or the actual foundation is the blocks down here.
So that's what holds your, holds your, uh, actual house up, is that. Then it's tied down. On this
particular one, you need five tie downs. You got two there, you got two there, and one there. That's
five. You gotta have five on each side, so you got five here, and five on the back. We have eight
piers on this side, and we have eight piers on the back. They put two right up underneath the doors
always. So this door's got two, and that back door's got two. So they're making sure that is
nice and level. They just beat it, basically two by four down on the ground. That's, uh,
cut on a 45 on the bottom, or a point on the bottom, make it easier to drive.
Drive that in, and then they're going to put a screw in it, and then they're going to do the
same thing down there, and, uh, they'll get their level line, and then we'll dig a footing,
dig a hole to put concrete in, whatever you want to call it. So, uh, we're going to dig a hole.
It's usually about three to four inches deep, and it's going to be, I don't know, maybe, uh,
uh, 10 inches wide. So we got that, got that lined up, bro. Basically, that two by four over there
is going to be the end-all be-all, basically. They're going to, after we get the, the, uh,
footing in, concrete, whatever you want to call it, after we get that in, that is going to be
the reference point to everything. So they'll measure up four inches and make a mark, measure
up four inches down there and make a mark, and that will give them their, um, that will give
them their height for the next brick. So then they'll, uh, they'll make another one four inches
up, obviously, and keep going all the way to the top. It's going to take probably, I don't know,
five or six to get up there, probably five, five bricks to get up there. Might have to add a little
bit right here. It's a little low. Um, these bricks we're using, we're using, uh, classified utility
bricks. So they are a foot long. They're four inches high and four inches this way. So four
by four, or they're actually three and three quarter, but after you put the mortar in there,
it ends up being four. So you got four inch. So if you need a foot, you need, uh, four of them to
get you a foot. That one broke. That one broke. But we'll use those on half pieces. So when you
get to the end, every other end is a half piece. So either you start out at a half or you end up
at a half. So one or the other is half. So the reason you do that is so when you go around the
wall, it'll lock in. So you'll have finger joints basically on that side and you'll have finger
joints on this side to do it. But they're setting up their other, their other, um, stick there.
Oh, whatever you want to call it. And, uh, then they'll, uh, they'll get to working on it.
Okay, y'all, we got a string line up and we're pulling plastic back. So we don't,
we don't screw that up. We're going to, our string line, we're going to dig down a foot
below the string line. So basically we was worried here that we were not going to have enough,
but we're going to have plenty. So what we're going to do is, uh, we brought the string line
up eight inches on each side. We're going to go four inches on there. That's actually going to
be five inches over there. That's going to be four inches over there. And it's only going to be
about three inches here to make everything line up the way it's supposed to, but we're going to
make it go and, uh, we'll be good. We'll cut it out. See what we can get to here.
It's a, yeah, using the short shooter there to go down in the ground.
Basically we'll encapsulate, that's a big word for me,
encapsulate. We'll encapsulate the anchor points of the, uh, right there.
The tie down point. We'll encapsulate it in it. So we'll get it all tied in,
get a concrete port and, uh, see what we're looking at. So basically they just go down
there a little bit and then they check to see if they're a foot deep. As long as they're a foot or
more, they'll be good. We'll, uh, we'll end up, our footing will be underneath these two pillars here,
or partially underneath them. So we'll, uh, we'll be good here shortly. Basically we'll just throw
dirt up here. Then we'll take a rake and we'll rake it out. Get it cleaned up. Make it look a
little better, but, uh, we're going to dig this footing and then we're going to get the machina,
I mean the machine ready. We got the, usually we don't have power on these things, so we mix them
by hand, but today we got the machine because we got power. We also got the cutter here.
This, I need to cut some stuff. I got the cutter and I got the
the mixer, collard concrete, got the wheelbarrow, got buckets. They love buckets carrying their,
their mortar mix around them. So I've got five or six buckets, but we'll make sure we have enough.
We got knee pads on. He's ready here. We're, uh, we're cutting down and we're getting in there.
Okay, y'all, here's what the, here's what it looks like. We dug this out here and dug that
out there because there's going to be a porch on the front of it here or a little landing,
I would say. So that's what it's looking like. Nice flat bottom and, uh, should be good. So
we're going to, uh, get ready and start mixing concrete up and put it in there.
We'll mix them together. It'll be fine. See that, keep that rim clean. It makes it a lot easier job
here. This thing flat mixes concrete. I'm going to turn you around where you can see in here.
See that line he's patting to? He's checking the height.
That's telling him if he's good or not. You make sure there's nothing on the line there all the
He's coming right along, making our footing. Just getting it, uh, getting it dug in there.
He's going to do that little bit here by eye just to, uh, just want it to tie in basically to where
we do the rest of it. So we don't have to, uh, we don't have to fight it. Getting them underneath
our pillars, getting all that pushed back. So we'll be good here short. Okay, y'all it's 50
foot long in this house. We've, uh, started down here with a footing and this don't have to be
perfect because the, uh, there's going to be mortar on top of that. So you'll have a,
you'll have a way to level it up. But here we go. We're going to see, we're going all the way there.
That's how much concrete we got left.
We did the whole front of it and it took us 42 bags on a pilot and it took us 21, 22, 23.
We still got 23 on there. So that means it took us 21 bags, 21 bags to do the job.
21 bags going across there and we didn't waste anything. We didn't dump it anywhere else. 21
bags, $6 a bag. You can figure out what that costs and this is 2023 we're doing this in.
So the, uh, you can figure that out and you can multiply that up or down or sideways or however
you want to do it to make the number come out to what you want it to come out to. But
that's what the number is. So, all right, we'll, uh, get back when we start laying brick.
Okay, y'all, we got us a little bit of mortar mixed up,
getting a couple of buckets full. We're going to, uh, start, uh, laying these things here.
Okay, y'all, it's, uh, been very long here. Let's cut it here and, uh, give me a thumbs up for
filming it and we'll keep going the next video here. So catch you on the next one.