Transmission is a highway system for electricity that moves power from where it's made to where it's needed. Explore the power grid and why transmission is important! Learn more about transmission and our work at the Grid Deployment Office by visiting: www.energy.gov/gdo/transmission-siting-and-permitting-efforts.
Topics:
00:00: Introduction
00:20: What is the power grid and transmission?
02:36: How is the transmission system managed?
03:25: Who builds new transmission lines?
04:56: Who pays for transmission?
[Music]
[Music]
hi everyone my name is Adria Brooks and
I'm a senior technical adviser with the
grid deployment office at the department
of energy we're here today to talk about
transmission planning
101 so the power grid is a highway
system for electricity that moves power
from where it's made to where it's
needed without power grid we just can't
move electricity across the country so
the nation's power grid it has a really
important role in keeping the lights on
Heating and Cooling homes charging our
phones importantly electric vehicles
runting manufacturing facilities just
basically keeping all of our essential
Services going in the US so the power
system it's made up of many components
with have the power plants which
generate electricity the grid which
actually moves that electricity and then
load centers so this could be Urban
cities or rural communities the
transmission system is really akin to
the US interstate system system if you
want to think of that analogy so it's
meant to move large amount of
electricity generated power plants
across hundreds of miles to where we use
it you've likely seen transmission
towers these are the large multi-story
towers so 10 stories tall with long
cables um on your drives between cities
or just outside of cities now the
distribution system is a different
portion of the power grid that's more
akin to the vast network of local roads
that distributes electricity from the
transmission system so Interstate System
lots of power um into our homes and
businesses where we use significantly
less power than what is transmitted on
the transmission system and the
distribution system these are shorter
Towers smaller cables I bet if you look
outside your window right now youd
probably see them this is the system um
the power grid that actually brings
electricity into our homes into our
businesses so that's the power lines
themselves now those are connected to
what we call substations and the
substations go between the transmission
system the interstate system and the
distribution system the local Road
Network that we used to connect to to
use electricity in our homes substations
I'm sure you've seen these look like
enlarged foft parking lots there's lots
of metal containers I've heard these
once described as metal jellyfish which
I really liked a lot so substations they
exist on either end of the transmission
system again to help change the voltage
from these really high power that we
need to transmit electricity on the on
the transmission system down to the
lower voltages the lower power that we
actually use in our homes that we use in
the distribution
system so the electric grid is arguably
the most complex machine in the country
so the Planning and Building in that
system also reflects that complexity
different regions of the country manage
their parts of the grid differently so
in some regions of the country local
utilities like those that we pay our
utility bills to electric bills to they
plan and manage their own portion of the
power grid other regions of the country
those same utilities have come together
to form these larger Multistate planning
coordinators these grid coordinators
that do all the system planning and
operations regardless of which style of
management in a region all those
utilities are responsible to state and
federal regulation of the power
[Music]
grid so transmission planning can happen
in this bottom up or top down way in the
bottom up way those utilities that
manage the power system they create
transmission plans for their service
territory so they know their system
really well they know what new
transmission lines or maybe upgrades to
existing system are going to be needed
in the near term now those Central
Regional coordinators they also do some
top down
planning so in that case these Regional
coordinators are going to look at at a
whole region so multiple States multiple
utilities within those regions and
they're going to try to understand okay
what are Maybe larger transmission lines
that would help meet needs across all
these different disperate utilities they
would take in those bottomup plans from
their local utilities and they would
also do this top- down planning to help
create a more robust Regional Network
now once those plans are approved by the
utilities or by the regional coordinator
at the um in terms of electrical
reliability any new transmission lines
that are proposed would have to be cited
in permanent that's where the regulation
comes in or where those regulatory
bodies other state or federal come into
play that can take that process of both
sighting and perming that can take many
years sometimes as much as a decade and
the exact map or route of the
transmission lines can go through many
iterations so both The Regulators but
then also land owners who are going to
be impacted by lines get to have a say
on where the transmission lines go
that's one reason why the sighting
pering process can take so long is want
make sure that we're talking to all
those different communities and making
these
plans ultimately any customer paying
electricity bills we call them rate
payers in Industry they're paying for
those newer upgraded transmission lines
now those costs get spread over time and
across the many different regions that
are being serviced by the transmission
lines again transmission lines seem to
be long multiple utilities multiple
States those costs are spread out now
the regulatory bodies usually at the
state level they're in charge of making
sure that rate payers that we don't have
to pay too much of a cost increase at
any one
time that said the grid deployment
office where I work does have several
financing tools to help lower the cost
of these transmission investments in
certain
areas and it's also really really
important to highlight that paying for
grid upgrades does reap benefits in the
long term so by expanding the
transmission system and bringing more
the energy to the power grid consumers
are going to have access to clean and
reliable and affordable electricity for
years to come if you're interested in
more information on this topic you can
go to the Department of Energy's grid
deployment office website where we have
a number of resources available to learn
more