Naked Starship BIG Firing At Massey with NEW Flame Trench! FAA License Coming...

GREAT SPACEX
1K followers
131 Video Views·Jun 5, 2024
sound up the first ever SpaceX Starship
flame trench system at massie's test
site officially went into operation with
an impressive static fire of s26 opening
a new era for the Starship project and
everything today will be even better
with a new revelation about the faa's
flight 4 launch
authorization progress we also cannot
forget to mention the notable progress
of the second launch Tower at Starbase
and finally NASA Boeing and Ula are once
again determined to launch cft1 in the
next few days so if you're ready let's
dive into these on today's episode of
great SpaceX we are getting closer to
June 6th the launch date currently set
by SpaceX for flight 4 however
everything still depends on license from
the FAA many people worry that if the
FAA delays the licensing process the
launch schedule could be postponed but
recently a revelation shows that
everything will go as planned according
to journalist Christian Davenport who
has often provided extremely accurate
updates the faa's licensing will be
completed quickly on his X page he said
barring any last minute changes from
SpaceX that the FAA will have to approve
the license should be ready for start
ship's fourth launch attempt on Thursday
I'm told based on this statement we can
see optimistic signals SpaceX has now
tested all flight components including
hardware and launch systems so it is
likely that they won't make any more
changes the Revelation emphasized FAA
will have to approve meaning everything
is quite certain for the flight on
Thursday so when will the license be
issued on the previous flight the FAA
pushed everyone to the edge of suspense
when they announced Ed the license about
16 hours before the flight it's a
stimulating feeling but it affects the
preparations of SpaceX media
organizations and viewers schedules I
hope the license will be available a day
earlier around June 5th so everyone will
have enough time to prepare and be ready
for this flight all right we'll have to
wait for more updates now let's move to
the Massie test site to witness the
future of SpaceX the first test of the
flame trench system at the beginning of
last last month s26 was rolled to the
Massie test site on the big static fire
stand at that time we all predicted this
would be the first prototype to be
tested for static fire with the flame
trench system and everything came true
in particular this time we did not see
any road closure announcements from
Cameron County the reason is
understandable because the Massy test
site is not located near the main road
and was originally built from an old
shooting range that is a big advantage
of the Massy test site compared to the
other two sites on the afternoon of June
3rd testing began we can see that the
horizontal fuel tank also had a venting
process similar to the tests at the
launch site fuel then began to be loaded
onto s26 and frost signs shortly
appeared especially in the liquid
methane tank the frost then Rose but did
not cover the entire tank indicating
that the fuel in this test was not fully
loaded additionally SpaceX may have
loaded a liquid oxygen into the header
tank as this part also showed Frost when
everything was ready s 26's engines
fired up immediately we could see a
large layer of dust appearing on one
side of the test stand contrasting with
the effect spreading to many sides in
the old test stand this is thanks to the
flame trench system we also saw dust
Rising higher than the height of the
Prototype which is more than 50 m the
engine burned for about 7 seconds but it
is unclear how many engines were tested
in this run thus the flame trench system
had an impressive debut working
excellently in dissipating heat and
pressure from the engine thereby
ensuring the safety of both the vehicle
and surrounding infrastructure this
confirms spacex's decision to implement
this system it'll completely replace the
old system and help Elevate the Massie
test site to become the world's greatest
testing location in the future after
this test s26 may be returned to the
production site the next test object
will likely be S31 the Prototype that
that encountered problems during
cryogenic testing last month S31 will be
a very important prototype because it
may be the first to return to Star base
if the upcoming flights go smoothly
everything is really amazing not only
the test system but SpaceX is also
ramping up the launch system
significantly with the progress of the
second launch Tower after removing the
entire old system and completing the
padb demolition SpaceX is getting closer
to building the second tower currently
SpaceX is proceeding with pouring
concrete and building the First
Foundation after a period of clearing
the planned construction area meanwhile
there's movement on the main object the
launch Tower segment recent images from
the Kennedy Space Center in Florida
revealed that the last two Tower
segments have arrived at their planned
location ready to be transferred to the
Drone ship and commence the journey to
Starbase alongside these two Tower
segments two other crucial Parts the
mechazilla arm or Chopstick were also SP
spotted however it appears that these
parts may not constitute the entire
Chopstick suggesting that the remaining
parts might be delivered and moved later
following the previous timeline this
relocation process May span over a week
these segments will first arrive at the
Port of Brownsville before being
transferred to the Sanchez site to join
these seven Tower segments that arrived
last month to recap between the 13th and
the 20th of last month five Tower
segments were relocated to the Sanchez
site presently SpaceX has acquired seven
out of the nine Tower segments at
Starbase regarding the design many
predictions suggest that this launch
Tower will need to be taller to
accommodate Starship version one which
will conclude at s32 and b14 Starship
version 2 set for production this year
is expected to be even taller musk has
revealed that version two will stand at
24.4 M this means the current launch
Tower will still suffice for version 2
but long-term use will necessitate an
increase in height particularly with
version 3 reaching up to 150 M with only
nine segments currently achieving this
height in the second launch Tower might
not be feasible additionally Chopstick
May undergo some modifications possibly
with a slightly shorter design to reduce
overhead when working and increase
flexibility for later catching tasks
however we'll need to wait until all the
parts are assembled to confirm these
changes as for the construction timeline
it's a matter of speculation the pace of
construction depends on various factors
such as resource availability weather
conditions and unforeseen challenges
once construction begins it could take
several months to complete but an exact
timeline is difficult to predict without
more information but hey feel free to
share any updates or insights you have
on the construction progress in the
comment section I know some of you there
have some Insider information so go
ahead as previously mentioned the the
transportation of two Tower segments and
the Chopstick component is estimated to
take over a week to reach the port of
Brownsville following this assuming
SpaceX promptly moves them to Starbase
an additional week will likely be needed
as the parts must be shipped
individually subsequently the relocation
of all components from the Sanchez site
to the launch site typically takes about
2 weeks considering these factors it's
reasonable to project that SpaceX May
commence construction around mid
July regarding the construction schedule
SpaceX has demonstrated remarkable
efficiency in completing previous
systems at both Starbase and Florida
within approximately a year this
includes the olm launch Tower and
Chopstick drawing from these past
experiences I anticipate that the
current construction process will
proceed rapidly potentially wrapping up
within 3 to 4 months this would align
with a completion time frame around the
end of the year furthermore this
timeline aligns well with spacex's
overarching plans they are targeting the
super heavy catch in Flight 5 followed
by both stages in Flight six the
addition of the new launch Tower brings
this goal within the closer reach than
ever before do you agree with the
timelines I've outlined please respond
with yes or no in the comment section
and don't forget to like the video share
it and subscribe to the channel to
welcome the new system to Starbase in a
recent update from Florida NASA Boeing
and Ula have provided fresh insights
into the Starliner Mission according to
NASA's latest report both NASA and
Boeing teams have affirmed that the
Starliner spacecraft ula's Atlas 5
rocket and all ground support equipment
are in optimal condition and poised for
the next launch attempt the report
highlights that significant progress has
been made at the launch pad specifically
space launch complex 41 at Cape canary
space force station in Florida on June
2nd teams completed crucial work to
replace and test a failed power
distribution source that led to the halt
of the launch attempt on June 1st in the
prior launch attempt a scrub occurred at
tus 3 minutes and 5 Seconds it took some
time for teams to diagnose the cause of
the abort which was triggered
automatically by the launch sequencer
eventually it was identified as a slower
than expected performance from a
computer following Thal review and
troubleshooting by the Starliner Mission
management team multiple aspects were
examined including replacement
procedures after detailed discussions
the team gave the green light to proceed
intensively preparing both the teams and
hardware for the upcoming opportunity on
the 5th given the recent issues and the
importance of ensuring safety it's
understandable to have doubts about
starlander readiness for the June 5th
launch while it's possible that the
teams have addressed the issues
adequately there may still be lingering
concerns ultimately the decision to
proceed with the launch will depend on
the thoroughness of the preparations and
the confidence of the mission management
team it's a challenging situation but
prioritizing safety is Paramount as for
a prediction hell w it's difficult to
make a definitive call so everyone I
would advise against placing your bets
at this time well folks that's about it
for today's episode thank you so much
for tuning in and as always this has
been Kevin from great SpaceX until next
time keep looking up