noc19-mg15 Lecture 48: GERT

IIT Kanpur July 201
20 followers
Dec 3, 2023
Graphical Evaluation Review Technique (GERT), OR and AND statements, Logical Relationships
Oh welcome back my dear friends and
students a very good morning good
afternoon good evening to all of you and
as you know this is the da dm2 course
which is data analysis and decision
making to course under the NPTEL MOOC
CDs and this total course duration is
for 12 weeks which is 30 hours which
when converted into lectures it will be
16 number because each lecture is half
an hour and each week we have five
lectures of half an hour each and after
one each week we have assignments so we
are in the as you can see from the slide
we are in the fortieth lecture which is
in tenth week and we will start start a
small new topic about something to do
with with project management related one
which is in very generally specific in
nature another thing which I wanted to
mention that in the 49th and the 50th
lecture on the sessions would be
conducted by ms priyanka sharma a PhD
student she will basically be doing a
very specific examples in the area of
marketing trying to basically show that
how different type of very simple
modeling techniques not from out where
optimization point of view simple modern
techniques can be utilized for different
about decision-making specific to
marketing and my good name is reg Anand
and Sengupta from the Miami Department
at IIT Kanpur so I will start with the
the other topic in this xlix like 48
lecture then forty nine fifty through be
taken in the area for the specific
examples only examples and then starting
lemons and twelve ik will cover some
topic of Gert and other topics in the
area of da dm2 as already scheduled so
whenever you are doing some activities
so I'll give you very briefly about that
ideas of God and Q God which is
God is generalized review technique and
general evaluation review technique and
qgo it would be queueing generalize
evaluation and review technique now
whenever you are doing project
evaluation review technique or you are
doing critical path matter the main
concern is that when you start from the
source to the sink starting and there
are two ways how you do that one is
activity based on arc an activity based
on node where the activities with their
time duration with the probabilistic or
deterministic whether they're slacks or
difference of time between them will
basically denote on the node or the arc
depending on whether it is on the
activity on arc or activity on node now
the main difference between pert CPM and
Gert and queue Gert is that in many of
the cases they are looping looping
allowed means say for example you do one
work and then the work is not yet
completed in the full satisfaction then
it comes for rework like doing you are
doing some welding the welding work is
not proper so obviously there's some
rework is done or the design problem the
you when you're building up small
factory building up of all building up
house or trying to basically make some
material or make a machine a car
whatever there may be some problems
there may be some issues for which or
they may be as per the norm some rework
is needed it need not be only problems
that you face that you have to again do
that or rework so say for example you
doing some analyst
tempering process or where the work has
to be done by layers like you are doing
the painting so the painting has to be
coated consider you are doing a very
simple painting so red oxide is to be
used so that rust this iron pillars or
the are in chairs whatever you're
utilizing they are not affected by rust
so the it's a protection then you paint
it so if you do the work and again come
to do two or three different times
so obviously rework would be done so if
you want to consider the
simple concept I am giving very simple
examples if we consider those simple
concepts looping would be allowed for
which Gert and Hubert should be utilized
so activity network I'm implying port or
which is projective relation if we're
taking or CPM are by far the most common
forms of precedence diagram however they
do suffer from important limitations
particularly in settings of the rnd
like if you consider the rnd project of
trying to bc come up with a new product
in the market or trying to frota a new
fridge and you refrigerate a new AC a
different type of brand of car if you
want to test it just market it or you
want to basically come up with a new
drug or medicine whether for fever or
for say for example cough and cold so
you want to basically test it in the
market get the response how fast the
drug is able to relieve the pain and
then basically floated it in the market
and you want to do experience also
before on primates then basically check
its efficacy of the drug on human beings
and then again market it so however so
let me read the second point however
they do suffer from some important
limitations particularly in certain
settings such as R&D projects where
their underlying assumptions reflect the
complexity of the individual product
project settings a very complicated
project like building a factory or say
for example be building up a nuclear
nuclear plant or trying to basically
check that how the launching of say for
example in sat this satellite should be
done done I'm considering the work being
done by say for example bark by is row
so for example situations such as
multiple branching such there is a
success or there is a failure of the
project again you do the reworks so
there are pro mystic branching methods
like you float a product there is 40
purchase chance the product will be
except with my in the market with good
demand 30% may be the case with the
product attacks etc with a low demand
and 10% with the case where the
projective product is not at all
accepted so in the broad mystic
branching and repeating activities via
the feedback loops which are frequently
found in experiments or R&D projects
cannot be taken into consideration when
you are doing the project evaluation
review technique or the CPM method as a
result graphical evaluation and review
technique Girt would be employed or can
be employed to offer an alternative
diagram modeling option for projects
that are faced with these additional
complexities so Girt creates an visual
method for rendering the networked
logical flow so how you go from all the
concept will be from the left to the
right so if you're going from activity 1
to 2 2 to 3 and then once three is done
again you come back to two to route some
of you work so all these things would be
considered and in very minor details in
the gut process so God creates a vision
method for rendering Network logic to
precedence diagram diagramming with the
added flexibility to demonstrate Network
complexities hence one uses God when one
wants to analyze terminal networks that
contains activities that have a
probability of occurrence associated
with them and we intend to find the
probability that the node is realized
so the flow which is happens on the left
or the right so Gert also treats the
possibility that the time to perform an
activity is not constant so it's
probably stick so you if you if somebody
has done part and CPM I'm not going to
go into details of them they would be a
most probabilistic time more pessimistic
time then most optimistic time and the
most probable time so you take these
values of T suffix a T suffix B and T
suffix M and do the calculation
considering the type of distribution for
the time duration would be there for
each and activity which you do in
importance CPM so Gert creates the
plausibility that a time to perform an
activity is not a constant but a random
very
with a certain distribution and we
intend to find the conditional moment
generating function of the elapsed time
required to traverse between two nodes
to activities such that we are able to
find the particular distribution the
variance the mean the median based on
which we can find out the average time
and the variances if at all
from node 1 to node n considering there
are n number of nodes from the start to
the finish for that job in Gert the
branches of the network are described by
two or more parameters which are what is
the probability that the branch will be
traversed so obviously as I said product
being successful 30 40 % product not
means that successful 30 percent and
product me in a failure by can be 20
percent say for example you are doing
some project where you are on the main
engineer chief engineer of an X oil
exploration plant or a company and you
want to basically test whether their
oils in some base in base in a really
can we go the very base in you can make
a ribbon see it can mean a Nazi whatever
it is and you want to basically do some
test marketing of the type of of the
seabed or the floor where you want to
basically search further and the oil on
the minerals which are there considering
that you are searching for minerals also
so if you do do a test testing of the
surface of the geophysical
characteristics of the rock surface then
obviously it will give you it can give
you different hints in one case it can
be it is a high probability that good
quality of of petroleum or may be there
in the second case there is a Everage
probability that the petroleum or would
be there and in the third case the gay
I'm only considering three cases so the
third case can be the probability of
getting in or is very less so in in both
the cases you will basically go for a
drilling experiment or drilling
exploration and if the probability is
very high then the drill would give you
different high levels of of petroleum or
if the probability of finding or is
medium then the then the actual chance
of getting the petroleum more would be
much less than the first case and
in the case when the the actual the
testing scientific testing which you did
geophysical testing which you did
geological testing which you did if the
probability of finding an on the
Petrillo more is less obviously in the
later case when you actually drill it
will be much less so they can be
different ways how we can implement that
that overall thing so probability would
be there there would be a probability
distribution Oh point one point number
two if you remember I just I mentioned
that you do some geophysical or
geological test and then you basically
go for the drilling so obviously the
probability of getting an ore would
depend on what type of mark the rock
circus surface which you have which is
that the rock surface quality the
probability of finding a particular type
type of rock surface will dictate what
is the probability in the later say
stage so stage two when you're drilling
would be dependent on stage one such
that you will basically have a
conditional distribution of finding and
the actual or when you drill so say for
example if you if you have three stages
and the consider the stages are like
this you'd you find doing a geophysical
test then you drill and then you market
the ores consider you have already gone
into a contract with different type of
companies where you will market the Mun
the Petroleum ores so if if the
probability of you making a profit
depending on whatever the investment
which you have done in third stage where
you're basically marketing it it will
depend on what is the probability of the
second step or actually finding the ore
and it will also depend on what is the
probability of the experiment which you
have done in trying to find out whether
actual good quality of ore will be
available so it will be stage by stage
the probabilities would be given and we
have very simple concept of Bayesian
analysis and if you remember those who
have done da dm1 I have very basically
covered the concept of base analysis and
how conditional distributions can be
utilized the second thing which would be
the parameter which would be required
for the Gert process would be the time
so the time taken to traverse the
branches if it if it is taken and also
remember the time taken to traverse a
branch from node 1 to node 2 or node I
to
no J considering there are no other
nodes between these two nodes ing that
can also be a problem is stick one so
consider that the work being is DHing
done by a risk consider the pic concept
of painting so though if the work is
being done by by automatic machines or
semi-automatic machines with respect to
the workers so obviously the time taken
in the initial case when you're using
machines would be much faster resolution
would may be much better but in the
other case obviously when using the
workers the precision may not be high
that high but no I mean but you should
consider the cost factor which is also
important when you are doing your
project so obviously time is is
probabilistic and the branch which is
taking is also probabilistic and and the
branches which are taken would basically
have a distribution as I mentioned it
can be also a conditional distribution
and the probability of the take of the
time being taken to traverse would also
have a particular distribution if you
remember I did miss in the pert and CPM
case we take the most optimistic most
pessimistic and the mean time of the or
the average time most probable time
based on which we we try to basically
find out so the components of the
stochastic a network because so if you
are coming to the the Gert network so
each path will take it will basically
have the probability which I'll mark so
it will have a probability so this is
the probability P a considering that if
I consider the path is 0 1 2 0 2 or I -
J the time taken to traverse from I to J
is given by T a and the corresponding
probability is given by P a so component
of stochastic networks are directed
branches which has arcs edges
transmission transmittances etcetera as
it is shown here
and will mention the starting and the
ending say for example by a and B
they would be logical nodes also add
vertices based on which you will proceed
from which direction to which direction
it will go it will have a flow and we'll
consider from the left from my left to
the right so if you are considering from
your side it will be from your left to
the right
a directed branch has one emanating node
from where it is going to start to be
described later on we'll come to that
later on
and one terminating node to be described
later on which we'll discuss that how it
starts and how it finishes so if you if
I consider very simply the logic would
be I start at say for example the
starting node and consider my ending
node is here but it may be possible that
all the paths which are taken are such
that I will follow all those paths in
order to basically reach my destination
so I'll consider this as a source s one
this as a sink s two and all the paths
would be meant or the nodes would be
mentioned in the logical sequence matter
so that means you can basically follow
any path and try to reach from the
source to the sink in in a certain
amount of time depending on that time
and also what the probabilities that
those pots would be followed so I've
given a time the row arrows and we're
over this each paths your probability of
taking that path along with the time to
take that part would be given I will
consider very simplistically the and/or
statements and and on logical statements
because based on that we will try to
basically build up the model so the
concept of exclusive-or is a logical
operations or process that outputs true
only when inputs differ so when when the
inputs are like this so input a and
input B if they are same the output is
basically 0 inputs are same so 0 0 gives
you a combination of 0 1 1 gives a
combination of 0 but if the inputs two
of them on obviously they can mean with
more than two and you can combine them
accordingly and in
puts our 1 0 and 0 1 opposite to each
other so it would mean that the overall
output would be one here no consider
this one how it can be consider the 1 is
an on 0 is enough
so let me draw the simple logic so I
have a I have B so this is
electricity is flowing some flow is
happening and consider the one first one
which means it is on connection is on
consider the second one is zero that
means there is no connection so still
current flows from A to B hence the
output is 1 so this takes care of this
one point on the diagram which I stated
now consider I go for the second one I
consider I plus 1 here I'll use the blue
color here now on the green color so it
is easy so this is zero so the first one
is off second one is on
so again the current flows from A to B
so that K takes care of the the red
marked one where opposite reactions from
on opposite output from two different
inputs give you the output is positive
or one now considered the other one
which is marked in yellow so let me
erase this so and come to this example
later on so with with examples I'll it
will be much easier for me to explain so
you have yes yes note and the output
actual output is zero
so in this case we will consider the if
the outputs are opposite to each other
the output since the output is happening
from a and B which are taken as an input
for the final decision if they are
opposite then your actual output which
is happening from a and B is yes and if
the outputs are from a and B which are
the inputs from a and B are same then
the combined effect would be unknown so
the truth table for the a XOR B which is
exclusive ORS would be utilized in such
a way that a 1 B 1 output is 0 a 0 B 0
output is 0 a 1 B 0 output is 1 and a 0
B 1 output is 1 now I go to the
inclusive or on also known as the
alternation it is a logical operation
that outputs are true only if one or
more of its operands are true so in this
case we will consider like this so this
a or B table would be output a is 0 null
or null means it's negative output B is
is considered as null in that case you
will basically have the total output so
both are no no output is no the moment
one of them is yes
in that case the output for a 1 B 0 is 1
a 1 B 1 is 1 and a 0 B 1 is 1 which
means a 1 B 0 1 a 0 B 1 1 a 1 B 1 is 1
so all these three things are true
statement considering the moment you
have any one of them or more than one of
them as truth statements in the end and
the logical statement you will consider
that if both of them not true then only
you will have the truth statement
otherwise not that means if a is 0 B 0
obviously it will be 0 if a is 1 or B is
1 that means if a is 1 B 0 or a 0 and B
is 1 in both the cases the truth
statement will be a null or zero none
means it's false and only if a and B
both are true you'll basically have the
truth step and s 1 so this is an and
logical operation that outputs are true
if and only if both operands are true
and the truth table for a and B are
given now in this case we will formulate
with the symbols for the Girt so the
exclusive-or would be a triangle
operator with a vertical line so the
realization of any branch leading into
the node causes the node to be realized
however one and only one of the branches
leading to this node can be realized at
any given point of time so it is an
exclusive or inclusive our would be the
triangle only so the realization of any
branch leading into the node causes the
node to be realized the time of
realization is the smallest of the
consider there are different time
periods you will take the minimum of
them so it says that the time of
realization is the smallest of the
completion time so although all the
activities leading into the inclusive or
node and the on end node would be the
node will be realized only if all the
branches leading to the nora realize the
time of realization would be the maximum
of them so in this case you will take
the minimum and in this case you will
take the maximum
and based on that you will try to
basically formulate the got network in
the DNS deterministic sense and the
probabilistic sense also you will have
different symbols so if all the branches
emanating from the nodes are taken if
the node is realized that is all the
branches emanating from this have a peep
animated equal so the if you basically
find out the probability in the sense
and if the probability of traversing
those paths is obviously one that is
they have to be traversed and obviously
the corresponding probability would be
one and if exactly one of the branches
so in the initial case they would be the
branches would be such that the path
should be taken with probability 1 and
in the second case when the
probabilistic exactly one branch
emanating from the node is taken if the
node is realized and in that case all
the branches emanating from the nodes
would have taken so it doesn't mean the
flow is going to happen in such a way
that only one path is taken in the first
case so there are branches or are taken
and all are with probability 1 and in
the second case probably stick one
exactly one of the branches emanating
from that node would taken with the
corner corresponding probabilities
already mentioned so now if we combine
the whole combinations which will come
out from from this probabilistic
deterministic exclusive this and on our
concepts are like this see in the first
case it is an exclusive or and a
deterministic one you have the symbol as
as given like a parachute which is put
on a horizontal plane now in the
exclusive order probabilistic one you
have the diamond-shaped and in the first
case the parachute with the base in the
third case inclusive or a deterministic
one who are parachute without the base
and in the inclusive order probably
coining of the diamond-shaped without
the base which was then in the second
case and the a non deterministic part
and the and the probabilistic part with
the circular one and the parachute which
is 100 and 180 degrees opposite so with
this I will end this 48th lecture and as
I told you already the 49th and the 50th
lecture for this week which is the 10th
week would be examples
simple examples from the area of
marketing in related areas will be taken
by a PhD student and she'll basically
discuss the overall application of these
methods which are quite heavily used in
the concept of marketing in the concept
of of statistical learning in the area
of say for example flow process in
mechanical engineering in operation
research in a big way so thank you for
your edition and I have a nice day thank
you