In the factory, the transformer ratio of each tap and the vector group are verified during production and acceptance testing. On site, ratio and magnetization current measurements are performed in order to assess possible winding damage, such as short circuits between windings or between turns. With the CPC 100, the ratio and magnetization current or excitation current can be measured at the same time.
Interested in power transformer testing? – Watch all of our videos: https://youtube.com/playlist?list=PLzmbZeI1bhu_22G4fDZqRuRPdn3l6I8b7
Interested in testing primary assets? – Watch all of our videos: https://youtube.com/playlist?list=PL5F0FD9968998E6E7
Get more Information about CPC 100: https://www.omicronenergy.com/en/products/cpc-100/
In the factory, the transformer ratio of each tap in the vector group are verified during production and acceptance testing.
On site, ratio and magnetization current measurements are performed in order to assess possible winding damage, such as short circuits between windings or between turns.
With the CPC-100, the ratio and magnetization current, or excitation current, can be measured at the same time.
At the transformer's primary side, high voltage is applied to one phase.
The applied voltage and the load current are measured internally.
The secondary voltage is connected to the CPC's voltage measurement input.
All quantities are measured in amplitude and phase.
The ratio of these voltages, equaling the turns ratio, is calculated and displayed along with the magnetizing current, and the deviation from the nominal ratio is displayed.
For transformers with an on-load tap changer, the CPC simplifies the process by combining the measurements for all taps in one test run.
Each time the user operates the tap changer, the ratio measurement is automatically performed.
For each tap, the CPC measures and displays ratio, signal phase angle, and the deviation from the nominal ratio in percent.
The transformer's condition is evaluated by comparing these results to specifications, factory testing results, or across transformer phases.