Voltage-Based-Timing measurement, or VTM, indicates that the voltage of a medium voltage switchgear in service is used to detect the state of the main contacts.
The easiest way to do this is to use the Voltage Detection System, or VDS, of the switchgear.
In this video, Andreas Nenning, OMICRON product manager of the CIBANO 500, shows how this is done:
00:00 - Introduction 01:16 - How to connect to the VDS interface with the circuit breaker test set 02:54 - How to accurately measure the states of the main contacts 03:49 - How to record the voltages of the primary conductors and how to get the calculated operation times.
Hi, my name is Andreas Nenning and in this short video I'm going to show you how to perform
a VTM measurement.
VTM stands for Voltage Detection System and this abbreviation indicates that voltage is
used to detect the state of the main contacts on a switchgear.
Therefore we use the Voltage Detection System.
The purpose of this system is to show the state of the primary conductors.
If there is a dangerous voltage, errors are shown.
On this specific switchgear we see here on the left side on feeder 1 a VDS system, grounding,
disconnector, disconnector, here the busbar, feeder 2, same thing, VDS, disconnector, grounding
and here the circuit breaker which actually supplies the energy to the substation and
here we have the relay which controls the circuit breaker.
By opening the circuit breaker the feeder 1 and 2 become de-energized.
To capture the operating time we have to connect to the trip and to the close signals, therefore
you need the schematics to identify the correct connection points.
In our case we get the trip signal from X2-72, the close trigger from X2-76 and the neutral
is connected to X2-31.
So let's connect our test device to the switchgear.
We will start with the VDS system.
We will use the so-called A cable to connect to the Voltage Detection System.
Here we connect the neutral to the bottom, then A1 to L1, A2 to L2 and A3 goes to L3.
The other side of the A cable goes to A1, A2, A3 and AN.
B1, B2 and BN will be used to connect to the X2 terminal.
B1 goes to 72, B2 goes to 76 and BN goes to 31.
On the Sibano side the B cable goes to B1, B2 and BN.
Now we can perform the test and therefore we use the primary test manager.
Ideally we have the test already configured in PTM, so we press the start button, the
test gets transferred to the Sibano and by starting the device gets armed and waiting
for the trigger input.
The trigger comes from the relay, we press the operation button there and operate the
breaker.
Now we get the results shown in our primary test manager.
On top we see the states of the main contacts, in the middle we see the voltage of the primary
conductors and by switching to the table view we get the calculated operating times.
Now we can also perform the open operation.
We start the test on our primary test manager, the data gets transferred to the Sibano, the
start button gets blue, we press the start button and now the Sibano waits for the trigger
input.
The trigger comes from the relay, so we go to the relay and operate the breaker.
Now we see the captured values in PTM and the calculated trip times.
By comparing these results with the factory acceptance test, please keep in mind those
are usually offline tests.
Thanks for watching this short video about how in-service voltage timing tests can be
applied on a switchgear.