FITCHBURG — The Department of Public Works advises residents of the following work that will be done, weather permitting, during the week of May 11, 2026.

Road Construction

Monday to Sunday 12 a.m. to 12 p.m.

River Street Bridge: MassDOT’s contractor Northern Construction has implemented a detour on the River Street Bridge. All southbound traffic will follow the West Street detour. Northbound traffic will be maintained.

Newton Place: Newton Place from Main Street to Boulder Drive will be closed to traffic. Monday — Friday, 7 a.m. to 5 p.m. (expect road closures, traffic delays and/or detours).

Combination Sanitary Sewer/Storm Drain Separation Project

Parking near the construction zone will not be allowed. GVC will be performing the following work:

Mechanic Street– new drainage installation

Circle Street/Main Street/Prospect Street – temporary water main installation

High Street – sidewalk preparation & paving

Unitil will be performing the following work:

High Street – gas main relocation

MTK will be performing the following work:

High Street – curbing installation

PROCUT will be performing the following work:

Wood Place – sawcutting

Main Street Water Main Improvements

Service interruptions to abutting properties are not anticipated.

JA Polito will be performing the following work: Water main installation on Main Street between Day Street and North Street.

Water Street Bridge Replacement

MIG will be performing the following work: Completing sewer work and paving on Boulder Drive. Local traffic will have  access to ExPress gas station and the parking lot at 310 Main Street. Installation of sewer on Main Street and Water Street. Main Street traffic will be restricted to one lane in each direction between Blossom Street and Snow Street. Northbound traffic on the Water Street Bridge will be diverted  to the Putnam Street Bridge.

Pipeline Replacement

Unitil and its subcontractors Neuco and Path Mechanical will be conducting natural  gas pipeline upgrade projects on Blossom Street from Main Street to Ross Street;  Main Street from Wallace Ave to Blossom Street and the following streets: Middle  Street, Railroad Street, Water Street Lane, 2nd Street, 3rd Street, 4th Street, Granite  Street, Salem Street, Spruce Street, Hale Street, Lynn Street, and Beekman Street.

Minor traffic impacts

Pothole repairs, citywide. Stormwater maintenance to prevent flooding from blocked catch basins. Repair water gate boxes at various locations throughout the city. Various repairs of the existing drainage infrastructure.

Hydrants, city-wide — inspecting hydrants for any plow/winter damage.

Hydrant flushing on the Low System (hydrants with black tops) in the John Fitch Hwy,  Water Street, Summer Street, Bemis Road, Airport Road and Crawford Street areas to  include all side/intersecting streets.

Street Sweeping will finish in Ward 1 and will commence in Ward 2 midweek. Residents  and business owners are asked to sweep sidewalks in front of their homes ahead of their  scheduled date. Sand should be placed in wind rows – not in piles – so that the equipment  can successfully remove it. A complete schedule is available on the City of Fitchburg’s  website.

A complete schedule is available on the City of Fitchburg’s website. Use SeeClickFix to report maintenance requests or concerns including potholes, sidewalks, signs/ signals, lights, parks, catch basins or manholes. Call the DPW dispatcher at 978-829-1900 with any immediate request including weather-related events (snow, wind, ice, flooding) or sewage backups.