What is Expected Monetary Value (EMV)? | Expected Monetary Value (EMV) Calculation with Examples

Policy Pros
2 followers
5 Video Views·Apr 2, 2026
AI Generated·May contain errors
What is expected monetary value? According to the PM book guide,
expected monetary value analysis is a statistical concept that calculates the average outcomes when
the future includes the scenarios that may or may not happen. It is an important concept in
project risk management which is used for all types of projects to make a quantitative risk
analysis. Expected monetary value calculation relies on measuring the probability and impact
of each risk. Probability refers to the possibility of occurrence of a condition or an event.
How to calculate the expected monetary value? There are three steps to be followed.
1. Calculate the probability of occurrence of each risk.
2. Calculate the impact of each risk as a monetary value.
3. Multiply the probability by impact. Example. You are managing a software
development project and identified a risk related to market demand.
The possibility of risk is 20% and if it occurs you will lose 10,000 USD.
Expected monetary value can be calculated as follows. Probability of occurrence.
20%. Impact of risk. 10,000 USD.
Expected monetary value equals to 20% times minus 10,000 USD equals to minus 2,000 USD.
Benefits of expected monetary value analysis. Enables to calculate contingency reserve.
Improves statistical thinking. Improves decision making.
Helps to select the risk management alternative which requires less cost.
Helps to calculate the cost needed to outcome of all uncertain events.
Forces the project manager to make cost savings during the execution.
This technique does not require additional cost, it only requires an expert to make
risk calculations. It can be used in conjunction with decision tree analysis.
Limitations of expected monetary value. This technique gives realistic results when
there is a large number of risks in the project. It is suitable for large and complex projects.
It is not used in small sized projects in general.
The impact of risk calculation as a monetary value may be difficult in some cases.
The expert who is making this analysis may affect the result because of his or her personal
decisions and bias. If the positive and negative risks are not identified properly,
the result would be misleading.