How Brampton businesses are coping with the delayed Hurontario LRT
1 Video View·Nov 28, 2026
0:00 Progress update on the Huron Ontario LRT and impact on local businesses
0:18 Challenges faced by Brampton businesses due to construction and turning restrictions
1:28 Impact of construction on business operations and customer access
2:21 Ongoing assessment work and plans for the underground LRT segment in Brampton
3:10 Long-term vision and optimism for the LRT's future benefits to Brampton
Construction of the Hazel McCallion LRT line is causing significant financial strain for businesses in Brampton, particularly north of Derry. While owners struggle with traffic restrictions and dust, early assessment work for the underground portion is beginning. Despite current hardships, some local stakeholders remain optimistic about the long-term urban development and growth.
So we gave you a progress update on the Huron Ontario LRT
plus we told you how construction
is hurting local businesses.
But what's happening with the Brampton portion of the Hazel McCallion
line? Just to recap, there are 19 stops a part of the Here Ontario LRT,
with three of them in
Brampton. But just like what we saw
in the Mississauga neighborhood of Cooksville,
the long-term construction is also hurting businesses north of Derry.
The Brampton Business Centre is located on Huron Ontario near Steeles
and business owners
there are struggling with turning restrictions.
It's affected us a lot because people can't turn
in on the street into the business and
now because of how it's set up,
people have to make a whole turn around just to come into
the business area.
Every day it's like less and less people
are able to come because they just don't want
to make a turn which is obstructing everything.
And it takes another 15 to 20 minutes just to get around.
So we're losing clients.
The sale is cut at some time, approximately in half.
Because the left turn and the construction, people come in for lunch.
And after waiting in that long line, they decide to turn back.
Or they cannot even make a left turn there to come in.
So we have to lose lots of customers that way.
Sometimes 20 minutes to change.
If we do change it maybe for a few seconds,
by the time two cars come through, then that's about it.
We have to wait again for it.
Plus,
it doesn't help
when your patio...
It faces construction.
Like a customer is sitting in the patio, right?
So all the dust particles and is like everything is coming up
and so their food and everything
is just come down like the dust will be coming
and they'll complain to us and we have to
switch them to the like inside again.
We don't know like what time they will come
and like block the road and yeah so that doesn't
make sense to us and it's a little bit difficult
for us to manage everything.
Metrolinx tells us that the work on this part of the LRT is ongoing.
And any businesses who have any concerns should reach out
to their community engagement office.
The plan for Brampton's portion of the LRT doesn't just stop at Steels
Crews have started drilling boreholes along Main Street
and the surrounding streets to
gather critical information related to the three-kilometer portion
of the LRT that is expected to be at least partially underground.
One business owner that we spoke to hopes the disruption
I have no idea how it will impact our business with an underground dig.
I'm hoping and praying that it will be transparent to us.
They all do their work underground. I'm fine with that.
But if it starts affecting our business,
like people can't easily come to our place,
then that's a different issue.
So I just hope they can finish it very, very quickly.
Metrolink says the early assessment work will go
into the spring of 2027.
While the transit agency is not providing
a completion date for the Hazel McCallion line.
Considering the delays and the construction woes,
there is still optimism regarding what
this LRT will bring to Brampton once it's completed.
One downtown landlord feels
the short-term pain will be a long-term gain.
I think it's very positive,
so it's encouraging and it's pushing people to say,
How can we develop a more urban form now
that we have this type of infrastructure and become
better for the future. I think it's taken
a while to get them to that point where they
decided to go underground.
I think the historic downtown of Brampton is an incredibly important
special place and doing it right is very important
for the city more than a lot of people I think
understand and it's an investment that's required
and it will be a huge piece of this city's history.
Nav Nanwa, CBC News, Brampton.