How close is the Hurontario LRT to being finished?
Nov 26, 2026
Video Summary
AI GeneratedThe Hurontario LRT project, an 18-kilometer line with 19 stops, has faced delays due to the pandemic and construction hurdles. While the province reports significant progress with over 80% of track work complete, an official opening date remains undetermined. Meanwhile, preliminary geotechnical work has begun for the future downtown Brampton extension.
How close is the Huron Ontario LRT to being finished?
The 18-kilometer Hazel McCallion line
that will feature 19 stops along Huron Ontario Street
was supposed to be done in the fall of 2024.
But the pandemic and construction delays
pushed that back, leaving many wondering what's going on?
But recent comments made by Ontario's
The U.S. Transportation Minister seemed
to indicate a lot of progress is being made.
Look, we've been making a significant progress on that line.
We've completed over 80% of the track work.
We have civil construction work happening
on it almost every single day.
We've got crews mobilized almost seven days
a week on the Huron Ontario LRT.
This progress update has one transit advocate surprised.
I've been taking the bus,
I've been driving up Huron Ontario and down Huron Ontario,
and what I've been observing is that there's
a really big difference between what's been happening
in the Brampton stretch, which is north of the 407 up to Steeles,
and in the Mississauga stretch,
which is south of 407 all the way down to Port Credit.
Work that was being done in the south side in Mississauga
that took three years, four years, five years,
six years, is being done in about two years here.
So, I don't know how or why the project has suddenly accelerated.
Maybe it's just that they're aware of the finish line
and they really want to get there.
Speaking of Brampton,
residents also got an update on the 3-kilometer portion of the LRT
that will extend into downtown
and is expected to be at least partially underground.
The province says crews have started drilling
boreholes along Main Street and surrounding streets
to gather critical information about ground conditions.
Borehole drilling is very common on every one
of our infrastructure projects to understand the geotechnical.
This is a part of the tunnelling process, but for us, it marks another
milestone in our commitment to continue building across this province.
Metrolinx, the provincial transit agency responsible for the project,
says this early assessment work will continue through the spring.
They're doing the exploratory drilling right now,
tells us that we've got at least
10 years before we would actually see major construction
and maybe a train actually running on the line.
There's a lot of work that has to be done ahead.
Metrolinx wouldn't comment regarding how long
the Brampton extension would take,
but did say that the planning and design work is underway.
Despite the progress that is being made,
the most important question remains.
When can people start riding the Huron Ontario LRT?
Well, we asked Metrolinx.
And the transit agency says an opening date will be determined
when construction nears completion
and we move further into the testing and commissioning phase.
So for now, still no opening date.
Nav Nanwa, CBC News, Mississauga.