Yukon Energy terminates contract with Texas firm over Whitehorse battery project delays
Nov 25, 2026
AI Generated·May contain errors
Video Summary
AI GeneratedYukon Energy has terminated its contract with Texas-based SunGrid Solutions for the Whitehorse Battery Storage Project due to failure to meet completion deadlines. The project, aimed at reducing diesel reliance and managing electricity demand, will now be managed internally by Yukon Energy with a target completion date of early 2027.
Yukon Energy says it's taking a new approach
to the Whitehorse Battery Storage Project,
which includes terminating its contract with SunGrid Solutions.
The Texas-based contractor was hired in 2022.
Yukon Energy says it's taking too long to finish the job.
The project is intended to help
the territory transition away from diesel,
as well as manage electricity supply and demand.
Yukon Energy's Vice President of Engineering
and Capital Projects explains the decision.
Well, our contractor...
Had a substantial completion date that was in July of this year
and they didn't achieve
that substantial completion date
and so that was an issue with our contract and given that
issue we notified them that they were in default of the contract
and asked them to remedy that
default meaning get the project back on schedule.
That didn't happen.
So we've, after careful evaluation, decided to terminate the contractor
and take the project over ourselves.
Our total project value is $35 million, and the contractor had about
a $25 million contract within that $35 million,
and there is around $8.5 million remaining.
The project is on its way to completion.
There's still work that remains,
but there's no significant problems with that system right now.
So, the termination of the contract is...
It's something that we can do under the contract terms
and conditions that we have.
So it's just a step in the process.
Our contract allowed for termination
when the contractor was in default.
Now, that's sort of what follows next.
I'm not sure.
But at this time, there's no legal action.
We've just taken steps under our contract,
given the contractor wasn't performing per contract specifications.
Yukon Energy says it will now take over
the Whitehorse Battery Storage Project.
The corporation hopes to have it complete in early 2027.