DWR Rehabilitates Oroville Dam’s River Valve Outlet System.

Planet in Balance 🌎
1 follower
2 Video Views·Oct 8, 2026
AI Generated·May contain errors
This summer, the Department of Water Resources completed a project to refurbish Oroville Dam's
river valve outlet system, which is a critical feature of the dam. During dam construction in
the 1960s, water diversion tunnels were built to keep the Feather River flowing downstream.
The river valve system is located in one of the original diversion tunnels and has two outlets,
each equipped with two valves capable of releasing water from the deeper portions of Lake Oroville.
This water is much colder compared to surface water temperatures and makes a significant
difference in cooling the Feather River during extended periods of heat or during prolonged
droughts when Lake Oroville's water levels drop. The frigid water pulled from the bottom of the
reservoir supports Feather River fish hatchery operations and Central Valley fish populations,
including Chinook salmon and steelhead trout, which spawn each year in the Feather River below
the dam. Water temperatures are carefully monitored by DWR to support healthy fish
and meet environmental regulations. The river valve outlet project is an important project for
the State Water Project as we look to modernize our infrastructure to be prepared for the
challenges from our changing climate. This project helps us build on the operational
capabilities of Lake Oroville, giving us a safer way to access cold water down in the lower parts
of the lake. This is tremendously important for downstream salmon species and also an important
part of how we meet our dam safety requirements. Construction on the RVOS project started in
October 2022 with a location deep at the base of Oroville Dam requiring creative construction
management. Getting the location, we actually had to require barges to go up three quarters
of a mile up through a small tunnel to bring in all the materials, even those valves that are
required for construction, including the rebar. Even the concrete had to be either brought in
by barge or we had to go up and down through slick line. These are 72 inch diameter ball
valves which are very big to allow up to 4,000 cfs to be released. This is an important project
for DWR as well as we try to continue to work on the rehabilitation of other portions of the
State Water Project because it's all getting to be 60 years plus old and this is a true example
of us being able to work together with our contractors and within our expertise of DWR
to make a finished product that is now ready and commissioned to be used into the future.
With this major component of Oroville Dam refurbished, DWR continues its commitment to
being a reliable, sustainable and affordable water provider for the people and environment of California.