NYC Officials Hold Press Conference updating on the Cracked Building in Midtown Manhattan

Live News Network
1.4K followers
10 Video Views·Jul 7, 2026
NYC officials hold a press conference updating on the cracked building in midtown Manhattan at noon, July 7.
AI Generated·May contain errors
Video Summary
AI GeneratedCity officials and emergency responders are managing a critical structural failure at a construction site on East 42nd Street. A 37-story building undergoing commercial-to-residential conversion experienced buckling columns and sagging floors on the 21st level. While no injuries were reported and all workers are accounted for, the building remains unstable.
Good afternoon everyone. Around 8 a.m this morning, FDNY received reports of a structural issue
at an active construction site on East 42nd Street between 2nd and 3rd avenues. This is an existing
37-story building with active permits to convert it from a commercial office building to a
residential building. First responders from FDNY, NYSEM, and the Department of Buildings responded
to the call immediately and found structural issues on the 21st floor. Two structural
columns have buckled in addition to multiple cracks and sagging floors. The building remains
unstable. Since arriving on scene, we have witnessed additional movement in one of the
compromised columns. First responders and structural engineers are working closely
with the project engineer to develop plans to shore up the impacted floor. If the floor is
deemed to be secure, engineers will enter and begin shoring up the building. As we await the
arrivals of materials that will stabilize the building, DOB engineers have been investigating
with FDNY drones. This is an extremely serious situation and I am thankful to our first responders
for quickly arriving at the site and to New Yorkers for reacting calmly and with urgency.
I am grateful to report there have been no injuries at this time and that every worker has
been accounted for. The NYPD has instituted a frozen zone from 40th to 45th streets between
1st and 3rd avenues. These streets have been temporarily closed off to both pedestrian
and vehicular traffic. The NYPD is also deploying additional officers to ensure that the area
remains secure. I want to encourage New Yorkers to avoid the area until it has been deemed safe
to re-enter. As we work to secure this building and ensure that New Yorkers are safe, I want to
encourage New Yorkers to also continue to follow the instructions of those who are on the ground.
I want to thank the many government agencies who have worked closely with one another this morning
to protect the people of this city. FDNY coordinated with NYSA, NYPD officers are
keeping traffic moving and helping to keep New Yorkers out of the frozen zones. DOB inspectors
and engineers are managing an incredibly complex situation. On behalf of New York City, thank you.
Now I will pass it over to our fire commissioner, Lillian Bonsignore.
Good afternoon. At 7 57 this morning, the FDNY received a 911 call for 235 East 42nd Street.
The report was for bricks falling from the from the upper floors. Our units arrived very quickly
and did an assessment. At this moment, we have 150 fire and EMS personnel on scene, over 50 units.
Upon arrival, there was an assessment done and the building was determined to be unstable.
So we started evacuations of the building and the surrounding areas, establishing a collapse zone.
I'm going to turn this over to Chief of Department John Esposito to talk a little bit more about the
actual operations here. Good afternoon. Thank you, Commissioner. Thank you, Mr. Mayor.
So we arrived on the scene to the reports of buildings, bricks falling from the building.
We conducted the assessment. We put our firefighters into the building to conduct
the search. We were in touch with the construction crews. All workers were accounted for. There were
no injuries. It's a very serious situation. The box beams, the steel beams have started to bend
and deflect from the weight. We evacuated the building and started evacuations of surrounding
buildings and the building has continued to move since we've been on the scene. We have a frozen
zone and a collapse zone set up and we are working with the buildings department and the building
engineer to make sure that this is safe for our people and for all New Yorkers. I'm going to turn
over now to the Department of Buildings Commissioner. Hello everyone. Much of the initial
information, the setting has been already shared by the mayor and my colleagues. We have seen
both buckling and floor conditions that are impaired on the 21st floor. We both have
construction safety inspectors and construction safety engineers on site evaluating from the
street and vantage points set up across the street and to the west so we can monitor movement
of the building and the floors to understand what's happening on a continuous basis. Once we can
determine that it's safe to enter the building, we will then in concert with the contractors,
ownership, and with consultation with FDNY be able to deploy a plan to shore up that floor and
then continue to investigate further for any other weak points that need further help
and shoring. After that point, we will be able to investigate further if there's anything else that
we need to do scoping out from that area. The work of FDNY, I want to thank OEM FDNY for the work
they're doing to create the perimeter and the safety zone. We encourage everyone to please heed
our ask not to come to the area and right now the safety of the public is our top priority.
Once we have more, we'll make sure to share that information with the public.
So we have specialized tools that we can watch the building from and see movement even in
centimeters or fractions of an inch and since we arrived on the scene and put that
in place, we have seen continual movement.
It does mean that it is not yet stable. It is still a very serious and dangerous situation.
I think this is a minute-by-minute assessment and I'm thankful for the work of all of our city
workers in doing exactly that from the morning through this moment and then through the rest
of the day and as you heard from our DOB commissioner, the number one focus here
is the safety of New Yorkers. We're thankful that at this time there are no injuries.
Every worker is accounted for and now we are continuing to assess as soon as this building
is stable, it then opens up the possibilities for us to shore up the building but until that point,
we are still having to measure that. I know our DOB commissioner wanted to add a few details.
As an example of how information changes over time, the initial report that came in
was about bricks falling off the building. When arriving, we did not see evidence of that,
we're not seeing things come off. The compromise point, as you mentioned,
is something that we're monitoring and looking at. The chief, especially SDNY's drone unit,
has been integral to watching and seeing how that movement happens and so right now you have both
DOB staff, you have the contractors with beams that are tracking that and what we are focused
on and what we feel like the next step is making sure we can get into that 21st floor
to add additional emergency trusses to spread that load and be able to move on with the investigation.
So I will just add a few words before passing it over to my deputy mayor
for housing to share on that. When it comes to what this building is, as you said,
this is a commercial office building that is being renovated into a residential building
and as part of the renovations is what we have seen here today. I'll pass it over.
So if I understood the question, this is a building that was going through a office residential
conversion. It went through plan review and has gone through an extensive exhaustive review with
DOB over the last two years. What is happening now is an investigation of what is the cause
of why the undermining happened and so once we have that information we'll be able to share.
But as the mayor said, it's a conversion of an office building into a residential property
and with that comes certain code changes and structural requirements all of which have gone
through a plan review and now we're examining what's happened now and we'll check it against
the reviews the plan purpose. Oh sorry that was the question. So the existing it's 37 floors
with an addition of 11 floors above a 22 floor element. So 22 floors on one piece, 37 on the
taller part of the building and they were adding 11 floors above the 22 floors.
So right now there are 37 floors and they have popped out on the extension as well. So the
the extension has been built out and they have popped out on that part as well.
The concern is that since we have been on site in the early morning we have seen
continued shift of the structure and I'm going to pass it over to our chief of department to
add a little more detail there. The way this building is constructed it's a steel frame
building so it would not be a total collapse it would be more of a localized collapse
but that that remains our concern that it's moving it possibly. So I'll first just start
with the importance of safety at this time. We have evacuated not only the building but also
seven buildings around it. I really do appreciate the way in which New Yorkers have responded to
this situation. We've seen that they have followed the instructions that have been provided by first
responders on the ground and that has been immensely helpful to ensuring that those first
responders can be focused on the work at hand. I'm now going to pass it over to our
DOB commissioner to add to additional details. So because the the structural issue has to do with
load bearing columns what we bring in are emergency struts that will take on the load of that and be
applied throughout the floor to take on that load plus we may apply additional struts given that the
the there's there could be weakening or cracks somewhere else. So it's really emergency beams
emergency columns that are brought in and then they go and replace the load plus we may add
additional for extra security and safety. Thank you. Yes as we've discussed before there is
extensive work happening right now between the engineers, DOB staff, FDNY to evaluate the
situation on the level using the information that we're reading from the outside. Once we have a
secure plan we'll be able to bring the equipment that we have now on site after asking the
contractor to bring that forward so that we're ready to go once we have a plan.
You know I want to be honest with New Yorkers that this is a fast developing situation.
We are taking it minute by minute and I appreciate our city workers who have been on the forefront of
that. Every few minutes we are looking at a new assessment of the structure and of the possibilities
and the options that we have in front of us. When it comes to the New Yorkers who call these streets
their home we are going to be in touch with them as soon as we have any updates. What I will say
to them for now is thank you because despite the impact on their day they have responded calmly.
They have responded with urgency and to those New Yorkers who do not live in this neighborhood I
would say to steer clear of this area so that we can actually ensure the focus is on this response.
We will be sure to keep the public up to date with any new developments as we have them.
Right now we're going to go back to work to ensure that all of these incredible city workers
can do what they have been here doing since the morning which is looking to keep us all safe.
We are only going to allow New Yorkers to return back into these buildings when we are fully
confident that they are safe for them to do so. That safety is paramount for us in every decision
we're making right now. I think you heard from our DOB commissioner that there is an active
investigation underway as to what brought us to this point. Our focus right now is on making sure
that this site is safe, this building is safe, this neighborhood is safe. That investigation
however will continue because we want to make sure that these actions are not ones that are repeated.
Thank you all very much.