How Engineers Built a 275-Meter Dam Where a Mountain River Refused to Be Controlled

Hightech Road Bridge
23 followers
20 Video Views·Apr 5, 2026
High in the narrow valleys of northeastern Turkey, engineers faced one of the most unforgiving construction environments in modern dam engineering: a steep mountain river that cut violently through unstable rock and left almost no flat land for construction. To control this unpredictable flow, they built the 275-meter-tall Yusufeli Dam—the tallest dam in Turkey—by carving an underground powerhouse deep inside solid bedrock and installing three massive steel-lined pressure tunnels to drive 558 megawatts of hydroelectric power. Every stage of construction had to adapt to landslide-prone slopes, limited access roads, and extreme terrain that made conventional dam building nearly impossible
Stuffing a colossal block of concrete as tall as a 90-story skyscraper
into the crack between two sheer cliff walls, with the Kora River raging below,
one of the most violent and fastest flowing torrents on the planet.
Experts once looked at this design and called it a technical recklessness.
And yet Turkey actually turned that deadly landscape into the greatest construction
project in its history, the Yusufeli Megadam. And to make this monumental project possible,
some of the craziest construction methods ever attempted had to be deployed.
Suspending excavators weighing dozens of tons high in the air, carving thousands of meters of
spiral tunnels straight through the mountain, and cooling 4 million cubic meters of concrete
with a massive ice water system. How could humans possibly build a dam like this?
Join Mandarin Tech as we peel back every technical layer of this mega-engineering
miracle in today's video. Turkey's economic boom and rapid urbanization have pushed its
electricity demand to record levels. However, the country still relies heavily on imported
fossil fuels, forcing the government to search for alternative energy solutions.
The Yusufeli Megaproject was launched to take on that mission. To turn this strategy into reality,
engineers placed their hopes on the Kora River, one of the fastest flowing rivers in the world,
with an average discharge of about 278 cubic meters per second. This powerful kinetic energy
offers a hydropower potential of up to 10 billion kilowatt hours per year.
Even more importantly, the river's steep V-shaped valley creates exceptionally
favorable terrain conditions, allowing engineers to design a 275 meter high arch dam
capable of generating enormous pressure to drive the turbines. Once completed,
the megaproject is expected to supply electricity to about 2.5 million people
and significantly improve flood control across the downstream region.
In most major hydropower projects around the world, such as the Taipu Dam,
Three Gorges Dam, and Grand Coulee Dam, engineers chose a gravity dam design,
a massive concrete structure that stays stable mainly because of its own weight.
But at Yusufeli, this option was almost impossible. The Kora River valley is extremely narrow and deep,
with very steep mountain slopes on both sides. If a gravity dam had been built here,
the amount of concrete required would have been enormous, making construction costs unrealistic.
Instead, engineers selected a double curvature concrete arch dam design. Unlike a gravity dam,
an arch structure allows the reservoir's pressure to be transferred sideways into
the solid rock walls on both sides of the valley, rather than pushing entirely
downward onto the foundation. The natural V-shaped valley geometry in this area effectively turned
the surrounding cliffs into natural supports for the entire structure. Thanks to this design,
the dam could reach a height of nearly 275 meters while maintaining stability, significantly
reducing the volume of concrete required, and improving resistance to seismic forces.
An especially critical factor in the geologically complex region of northeastern Turkey. However,
one important question remained. Were the two valley walls strong enough to hold a dam nearly
275 meters tall? To answer this, engineers carried out a full 3D geological analysis of the entire
valley. They drilled hundreds of deep core samples, some reaching hundreds of meters into
the rock, to evaluate compressive strength, fracture conditions, and the natural layering
direction of the mountain mass. At the same time, all geological data were fed into numerical
simulation models to predict how the entire valley would respond under the pressure of billions of
cubic meters of stored water. Only after confirming that both mountain slopes could function as
reliable natural supports for the arch structure, was the plan to build Turkey's tallest dam officially
approved. Every second, nearly 278 cubic meters of water rushed through the Kuru Valley with
tremendous force. So before the Yusufeli Dam could even begin to rise, engineers first had to redirect
the entire river. To do this, they drilled and blasted a massive diversion tunnel straight
through the mountain. With a diameter of up to 11 meters and a length of about one kilometer,
this tunnel functioned like a giant bypass pipe, capturing the full flow of the Kuru River
and guiding it safely around the construction site before releasing it back downstream.
However, even after the main river flow was diverted and the riverbed was exposed, conditions
were still not safe enough to begin foundation excavation. To completely isolate the construction
zone, engineers built two temporary cofferdams, one upstream and one downstream, creating a dry
working area right in the middle of the valley. Yet a hidden technical risk still remained beneath
the riverbed. Groundwater could seep back into the excavation area due to pressure differences
between the upstream reservoir and the construction pit. To eliminate this threat, engineers drilled
as deep as 50 meters into the bedrock to install an underground seepage control curtain beneath the
river channel. This system effectively sealed hidden water pathways and stabilized the entire
foundation area, ensuring safe conditions for building one of Turkey's most ambitious hydropower
structures. To turn the two valley walls into true structural supports for a dam nearly 300 meters tall,
engineers could not rely on natural terrain alone. They had to firmly lock the dam into the mountain
using a massive steel anchoring system. Engineers drilled tens of meters deep into the bedrock
on both abutments of the dam, then installed large-diameter, high-strength steel anchor bars
into these boreholes. These anchors were injected with high-pressure cement grout to tightly bond
them with the surrounding rock, forming a network of steel roots that secured the dam body firmly to
the mountain slopes. In addition, this anchoring system helped seal natural fractures within the
mass, reducing the risk of block movement and significantly improving seismic resistance.
As a result, the entire arch structure could remain tightly pressed against the valley walls,
with extremely high stability under both water pressure and earthquake loading.
Nearly 300 meters below the valley floor, the Yusufeli construction site was almost completely
isolated from the world above. To make construction possible, engineers had to create an entirely new
transport route, a massive spiral access tunnel driven directly through the mountain. This tunnel
allowed heavy trucks carrying concrete, steel, and construction equipment to move continuously
between the mountain surface and the foundation level without being affected by steep terrain
or landslide risks. This underground route stretched about 2,420 meters in total length,
winding upward in a continuous spiral with a carefully controlled technical gradient
of around 18%. The spiral design effectively neutralized the extreme natural slope of the valley.
More importantly, it preserved the stability of the surrounding mountain slopes while turning
the tunnel into a vital transportation artery that sustained the entire Yusufeli megaproject
during peak construction periods. Under the harsh terrain conditions of the Karoo Valley,
conventional construction roads alone were not enough. Instead, engineers established a
three-dimensional logistics network operating simultaneously inside the mountain, along the
slopes, and even across the air above the valley. Steel cable systems were stretched directly between
the mountain sides, forming aerial transport corridors capable of lifting and moving equipment
weighing dozens of tons. Excavators, steel components, drilling equipment, and large
concrete buckets could all be suspended and delivered precisely to their required installation
points on the dam structure. At the same time, a high-capacity aggregate conveyor system was
installed along the mountain slopes to continuously supply crushed stone and sand from the crushing
plant to the batching station. After mixing, the concrete was transported down to the dam body
using specialized mixer trucks traveling through the internal spiral tunnel, ensuring that the
concrete always reached the placement zones within the allowable time limits required by structural
design. The total volume of concrete used at the Yusufeli Dam reached about four million cubic
meters. At this scale, transporting concrete from outside the construction site was almost impossible.
Instead, a large-scale system for coring, crushing, screening, and concrete batching was installed
directly above the construction area, forming a closed on-site supply chain. All the rock excavated
from slope cutting and spiral tunnel construction was reused and fed directly into the crushing and
screening system. Here, jaw crushers and cone crushers operated continuously to break large
rocks and classify them into coarse and fine aggregates according to the required grading
specifications. From the storage areas, the aggregates were automatically transferred through
conveyor systems hundreds of meters long and fed directly into the silos of the central batching
plant. The batching plant at Yusufeli was designed with extremely high capacity, mixing cement,
aggregates, water, and add mixtures into massive volumes of concrete every day. As soon as each
batch was completed, the fresh concrete was immediately discharged into mixer trucks or
large concrete buckets and transported to the cable crane launching platforms.
This on-site production system allowed the construction site to be fully self-sufficient
in materials and maintain a continuous daily concrete placement schedule throughout the dam
construction process. However, the continuous concrete placement process created a serious
physical risk, the heat released during cement hydration. When cement reacts with water to harden,
it releases a large amount of heat. If the concrete volume is too large, the temperature inside the
core of the structure can rise sharply. The temperature difference between the hot core
and the cooler outer surface can generate thermal stress, which may lead to internal cracking and
could seriously damage the load-bearing capacity of the dam. To eliminate this risk, a large capacity
industrial ice production plant was built right next to the batching station. During the mixing
process, instead of using normal water, engineers use tons of flake ice together with deeply chilled
water to reduce the initial temperature of the fresh concrete mixture below standard levels.
The dam body was constructed using a layered placement method divided into independent
vertical concrete blocks formed by a hydraulic climbing formwork system installed tightly along
both faces of the structure. To control thermal stress, a network of steel cooling pipes was
embedded inside the reinforcement cage before each concrete placement. Cold water at 4 degrees
Celsius was continuously circulated through this system 24 hours per day to absorb the heat released
from hydration inside the dam core. When the entire structure reached the final crest elevation
of 275 meters and achieved the design shrinkage level, specialized equipment was used to inject
high-pressure grout into the contraction joints. This mechanical operation locked the individual
concrete blocks together, officially forming a unified monolithic arch dam structure capable
of carrying the full structural load. At the same time as the concrete pouring process,
thousands of electronic sensors were embedded directly into the reinforcement cages,
creating a continuous structural monitoring network. This system included temperature
probes placed deep inside the core, which sent signals to automatically pump cold water through
the cooling pipe network, helping prevent the concrete from cracking due to excessive heat.
At the same time, displacement monitoring devices were installed throughout the structure
to record every vibration, shrinkage movement, or even the slightest deformation. All of this
data was continuously transmitted through fiber optic cables to the display system in the central
control room. Thanks to this system, engineers were able to monitor the structural health of
the dam around the clock, allowing them to immediately detect any hidden movement or
internal cracking that could not be seen by the human eye. With a reservoir capacity of up to 2.1
billion cubic meters, Usveli Dam was equipped with a multi-level combined spillway system
with a maximum total discharge capacity of 8,000 cubic meters per second, designed to prevent water
from overtopping the crest and destabilizing the steel anchoring system. This structure included
three spillway bays on top of the dam, operated by massive steel-lined radial gates. At the same
time, to reduce the load on the main dam body, two underground diversion tunnels, each 8.5 meters in
diameter, were drilled directly through the mountain core to carry water around the structure.
Because the valley was too narrow, the entire power generation complex of Usveli
was designed completely underground inside a gigantic artificial cavern, excavated deep into
the bedrock on the right bank. The system operates through three steel-lined penstocks that plunge
straight down into the ground, creating extremely high hydraulic pressure to drive three vertical
shaft Francis turbine units. The kinetic energy of the water spins the generator rotors, giving
the plant a total installed capacity of 558 megawatts or 186 megawatts per unit. After
passing through the turbines, the water is discharged through the downstream tunnel system
and flows back into the river. With this closed mechanical system, the Usveli megaproject supplies
an average of 1.88 billion kilowatt hours of electricity to the national grid each year.
That is enough to provide power for 2.5 million people, equal to the energy demand of an entire
megacity, making Usveli one of the strongest pillars of Turkey's national power grid.
Standing tall between steep rock walls, Usveli is not just a 275 meter high dam,
it is proof that human beings can force even the harshest terrain to operate on their terms. From
drilling through mountains to divert the Kora River, to locking the dam body into the canyon
walls with a gigantic steel anchoring system, to cooling millions of cubic meters of concrete so
the structure would not crack from the inside, this entire project was a chain of near-extreme
engineering solutions. But the greatest value of Usveli does not lie only in its size or its
record-breaking numbers. Its true value lies in this. It is a place where the chaotic power of
nature has been transformed into electricity, flood control, and a piece of infrastructure
capable of supporting millions of people for decades. That is why Usveli is not simply a
megadam. It is a statement that in the confrontation with rock, depth, and violent water, modern
engineering can still prevail. Thank you for joining Mandarin Tech in today's video. Do not
forget to like, subscribe, and turn on notifications so you can continue exploring more extraordinary
megaprojects with us.
