Funicular Trains Defy Gravity to Carry Skiers to Resort – How Did They Build That?

The Age of Rail
4 followers
6 Video Views·Nov 25, 2025
The car free Swiss village of Stoos needed an advanced funicular rail system to take tourists up its incredibly steep slope. Their first challenge: excavating a series of tunnels upwards, utilizing a form of drilling originally used to create ventilation shafts in mines.
To the beautiful mountains of Switzerland now and a challenging and innovative construction project
that really puts the fun in funicular. Do you even know what a funicular is? No? Let's stick around.
This is the Stussbahn funicular railway. Funicular railways solved the problem of
carrying passengers up steep slopes by pulling the carriages up with a single cable looped
over a pulley at the top. In 1933 the tiny village of Stuss opened its first funicular
which not only brought in the tourists but was also the main access into and out of this car-free
resort. 70 years later the alpine village wants to be better connected to the valley below.
The plan is for the new funicular to link Stuss with the town of Schwyz in the valley below.
The route will climb 2,500 feet in altitude on a single track that's over a mile long.
Three tunnels will be carved through the mountain at some of the steepest gradients ever attempted
48 degrees. At either end bridges will connect the near vertical mountain to horizontal station
platforms and engineers will have to design revolutionary carriages able to adjust to that
using radical hydraulic engineering. Reinventing a tried and tested transport system is one thing,
engineering and building it is another. The first challenge Bruno and his team face
is excavating a straight route up the mountain. In 2014 work begins on the first of three tunnels.
They turn to an innovative form of drilling originally used to create ventilation shafts
and mines called raised boring. The team expects excavating the initial 10-inch pilot holes to take
five days but partway through the drill piece breaks bringing the project to a halt.
A year behind schedule the team resumes excavating 30 feet of tunnel per week
blasting the primary holes and enlarging them with a special boring machine
before coating and sealing them with concrete. Finally in February 2017 three tunnels totaling
1,900 feet in length are finished. Next they need to create a carriage system that can handle the
extreme changes in gradient from steep mountain to flat station platform. Five years after
construction began the revolutionary Stussbahn funicular is almost operational. The team has one
final check, stress testing the prototype carriage systems at extreme gradients.
The radical funicular carriage system achieves what many thought was impossible.
Under test conditions the interior barrel-like cabins rotate horizontally at gradients of 110
percent and then back to zero again on the flat. Against the odds on December 17,
2017 the new Stussbahn funicular railway opens to the public. Two years over schedule
and about 30 million dollars over budget the build may not have run quite like clockwork
but within months Stuss with its incredible new railway is voted one of the top tourist
destinations on the planet.