Building massive foundations in the river for New Zealand's first extradosed bridge.

Hightech Road Bridge
22 followers
9 Video Views·Nov 13, 2025
The Wēiti River Bridge, the centerpiece of the O Mahurangi Penlink project, will become the first extradosed bridge to be built in New Zealand.
Watch the first stages of construction for the massive bridge foundations of the first pier that will rise up out of Wēiti River.
My name is Brent Van Bergen and I'm the piling engineer down here at Aumahurangi Penlink
where we are currently constructing the foundations for the Waiiti River Bridge.
It's 535 metres long and the central span is 175 metres. The new deck level will be
about 40 metres above the waterline which is about the same height as the Auckland Harbour Bridge.
There are 12 main supporting piles. They range from 1800 up to 3 metres in diameter and are 47
metres deep. The piles themselves are among some of the largest marine piles ever to be
constructed here in New Zealand which requires 360 cubic metres of concrete and about 70 tonnes of
reinforcing steel. There are four three metre piles located out in the Waiiti River so those
piles need to be constructed in a marine environment so it involves constructing staging
to get out there and then what we do is we drive sheet piles to form a cofferdam to effectively
enable us to de-water the area around the piles but also to be able to excavate all that soft
marine sediment near the surface. We excavate all that material in there and we cast a concrete
floor in there and that concrete floor will act as a gate for installing our piles. We then install
a couple of oversized casings to get us through that final little bit of soft material and then
the process is if we open drill so it's an open excavation down to the toe of the casing and then
we use two cranes to pitch a single casing on full length and then that gets lowered into the toe of
the pile. I'm currently standing in one of three cage segments that form a single pile cage. Due
to the length of the piles it's not possible to deliver one cage and install that vertically down
the piles so they come in these three segments. This cage gets joined together with two other
cages and gets lowered into the excavation and casing that we've previously installed. The diameter
of these piles is extremely tricky to deal with drilling an extremely large hole wanting that to
stay stable that we can install a cage and pour concrete. Each pile requires approximately 65
standard concrete trucks to provide enough concrete to fill the pile.
The pour itself took just over five hours to complete.