Terran R August 2025 Program Update

Tech Space
172 followers
August was a big month for the Terranar program. Let's recap key milestones across design,
build, test, and launch. This month, the team completed 18 component-level critical design
reviews, many of which were for the second stage engine, AonV, or fluids components.
All machined fluids components for the thrust structure have now been released,
including all valve components. The stage engineering teams, including structures,
mechanisms, and fluids, continue to work hard to close designs for Stage 1 and Stage 2.
Recently releasing Relativity's first composite parts and increasing their focus on reused
systems such as landing legs. The thrust structure build is complete. The thrust structure is one of
the most intricate and complex parts of the vehicle, so its build required tight collaboration
between dozens of teams across the company, as well as the introduction of advanced manufacturing
methods to enable high-rate production. In parallel, we finished welding the final Stage
1 barrels for first flight on the vertical friction stir welder. Now, all eight first
stage and two second stage barrels for Terranar's first flight have been welded. With barrels
complete, first stage tank welding has begun. The first circumferential friction stir weld is
complete, joining two fuel barrels together. Separately, welding on the first stage downcomer
is in progress. The manufacturing team activated the paint booth this month, marking another major
production capability now online at our factory. Manufacturing and assembly of the first flight
engine is complete. It has been shipped to NASA Stennis, where it will be installed on the stand
for acceptance testing. The factory test team activated the structural test stand in Long Beach
that will test the thrust structure in first and second stages. Activation was the culmination of
years of work and involved building structural and fluid systems, integrating data systems,
loading software, and configuring IT systems. The stand is capable of six million pounds of
compression, 170,000 pounds of shear, and pressures up to 250 pounds per square inch gauge.
The thrust structure was loaded onto the stand and began multi-week acceptance testing.
On the stand, we tested a flight case simulating Max-Q and are preparing for a hold-down case
replicating conditions on the launch pad. At NASA Stennis, we began hot firing a development article
of our second stage vacuum engine, Aeon-V. We successfully demonstrated operations across
throttle, mixture ratio, and gibble ranges. The first stage flight engine is being prepared for
upcoming acceptance testing on the second bay of the dual bay test stand.
Nine commodities tanks arrived at NASA Stennis for the A2 structural test stand. Once installed,
they'll be capable of storing 650,000 gallons of liquid oxygen, liquid natural gas, and liquid
nitrogen to support stage testing. In avionics, the team made significant progress on the path
to completing the vehicle level hardware in the loop testing this year. Initial avionics hardware
has been integrated into the system and ground software and equipment was used to successfully
send commands and receive data from ground hardware to avionics. The first version of vehicle
software has been deployed to the avionics system, laying the groundwork for future testing and
mission operations. At Cape Canaveral, site work continues to accelerate. This month, we completed
a major concrete pour for the transport erector cap. This TE cap will bear the loads of vertically
lifting a fully integrated Terranar vehicle while made it to the TE. Water tower fabrication is also
progressing with most of the large storage tank welded and installation of stanchions for above
ground piping systems is underway to support commodity flow across LC-16. From progress on
primary structures and engine testing to enabling infrastructure, August has been another busy
month on the path to Terranar's first flight. Stay tuned for more.