The Eddleston Water Project

The Beauty Of Nature
21 followers
12 Video Views·Apr 26, 2025
The Eddleston Water Project in Scotland aims to restore the natural flow of the Eddleston River to reduce flood risk, improve biodiversity and protect local communities. The project combines scientific research with sustainable management of the river environment and ecosystem.
Comments are disabled for this video.
The Edelston is a 70km square catchment with a typical mix of land uses including moorland,
rough grazing, forestry and improved pasture.
Located 20 miles from Edinburgh, the Edelston Water Project was established by Scottish
Government primarily to examine how the restoration of natural habitats and processes could help
reduce flooding to the towns of Edelston and Peebles downstream.
Led by Tweed Forum in the Scottish Borders, the Edelston Water Catchment was chosen because
it has a real flooding problem.
It was also in poor condition, having been channelised and embanked throughout most of
its length over 200 years ago, with little natural recovery since.
In 2011, one of the most comprehensive monitoring networks in the UK was installed in the catchment
in order to be able to monitor change and track the passage of individual storms as
the water moves down the catchment.
Meanwhile, Tweed Forum engaged with farmers, foresters and local communities to see if
they might host a variety of restoration measures.
The showcase of the project was the re-meandering of a 3.5km stretch of the main stem to reconnect
the river with the floodplain, which took place over several years on seven different
land holdings.
The main sections that we meandered were done in 2013, and that basically involved a machine
coming in and moving around, creating these bends and then allowing the river to do its
own work.
The following year, there was very high densities and numbers of invertebrates, but the variety
hasn't come back immediately.
That's taken time, and one of the delights is we've had 10 years of monitoring this to
show the gradual increase in diversity.
So it's a really important demonstration, if you like, of the gradual recovery of a
system from 200 years of being constrained.
The project also involved creating a number of ponds, which have a certain amount of freeboard
built in to store water.
We've created now 41 flood storage ponds, and they have dual purpose.
They're designed both to be good for ecology and to be good for holding back floods, and
we've got very good evidence to show that they're extremely good for particularly dragonfly
populations.
We've got huge increases in those across here.
And from a flood point of view, in the small sub-catchments where we've got quite a lot
of ponds, there they do have an impact on the floods.
Another key part of the Eddleston Water Project has been the installation of log structures
or flow restrictors.
So in total we've got, I think, 116 of these log structures now, and they were put in really
quite early on, right up in the headwaters.
And they're very simple.
They literally are a local tree felled across the stream.
This is not bringing in extra new material.
What happens is as the water level rises, it gets caught behind the logs and it spills
out into the immediate floodplain.
Probably the thing we've done most of is planting trees.
We've planted probably in the region of 350,000 predominantly native trees over 210 hectares.
These trees help interception, encouraging infiltration and transpiration and slowing
down overland flows.
They also help reduce thermal stress for salmonids by providing shade.
In all, work has taken place on over 20 different land holdings.
Because it's the Eddleston Water Project, and because there's a number of farmers involved
in it, I think we've all put our, by and large, our shoulder behind it to make it happen.
Aesthetically, it's very pleasing and visually very appealing, not just for me, but for other
land users and people that enjoy the countryside.
The results of the project have been dramatic.
Remeandering the main river has vastly improved the range of in-stream and riparian habitats,
notably pools and areas of fast-flowing gravel, which are key spawning sites for salmon.
And the salmon fishery is hugely important, bringing in £24 million a year to the area
and supporting over 500 jobs.
The log structures are proved to delay flood flows by between two and seven hours, and
the project has also shown that infiltration under mature native trees is up to eight times
greater than under adjacent sheep graze pastures.
We can show that the work so far have led to about almost a million pounds of flood
damages avoided downstream, on top of which you can do at least four times as much value
in terms of biodiversity, water quality and other aspects.
So this is really impressive figures.
It is hoped that the lessons learnt here can inform work elsewhere that will make communities,
infrastructure and wildlife more resilient to climate change in the future.