This video is mainly about masonry work and cement consumption for finishing works. This video helps masons doing their finishing works, bricklayers & other masonry contractors to understand the thumb rules for cement consumption, masonry and finishing works. It's important that we have thumb rules in our mind to avoid mistakes in construction activities i.e masonry, finishing works and cement consumption. In this video we will give you some thumb rule for masonry like how much cement we should use if we want to make 1Cum of brick wall, brick work, the thumb rules for finishing works & how much cement we should use if we want to make 1 Sqm finishing works like plastering, tiling, waterproofing.
Note- NOTE: ALL THE IMAGES/PICTURES SHOWN IN THE VIDEO BELONGS TO THE RESPECTED OWNERS AND NOT ME... I AM NOT THE OWNER OF ANY PICTURES SHOWED IN THE VIDEO ---------------------------------------------------------------------------------------------------------
Copyright Disclaimer Under Section 107 of the Copyright Act 1976, allowance is made for "fair use" for purposes such as criticism, comment, news reporting, teaching, scholarship, and research. Fair use is a use permitted by copyright statute that might otherwise be infringing. Non-profit, educational or personal use tips the balance in the favor of fair use.
Hello Friends Welcome to Knowledge Hub
Channel Let's Learn Together This is the
5th video of Thumb Rules Series Thumb
Rules for Machinery and Finishing Works
If you haven't watched the previous video in the Thumb Rules
Series you can find the link in the i button and in the description
In the previous videos we have seen Thumb Rules for Standard High Rise Building
Thumb Rules for Concrete Steel Shuttering
and Thumb Rules for Labours
In today's video we will look at the essential guidelines for machinery and finishing work
Essential Guidelines for Machinery and Finishing Tasks
First of all we will look into
brickwork We have a 9-inch construction
In 9-inch construction the number of bricks required is 500
In this we have mentioned the standard size of 190x90x90 the
number of bricks required per cubic meter is equal to 500 numbers
In the case of Hub Brickwork the number of bricks required is 60
In the case of Hub Brickwork the number of bricks required per cubic meter is equal
to 60 numbers Now we will see the Mix Ratio Machinery Thickness Mortar Thickness
Cement Requirement and Sand
Requirement: In the case of a 1 to 6
mortar ratio 1 for cement and 6 for
sand Machinery thickness is 200mm
Mortar thickness is 10mm Cement consumption is 1.4
bags per cubic meter Sand
consumption is 0.3 cubic meter
In the case of a 1 to 5 mix ratio 200mm is the
masonry thickness and the
mortar thickness is 10mm
Cement consumption is 1.7 bags per
cubic meter Sand consumption
is 0.25 cubic meter In the case of a 1 to 4 mix ratio
Brick masonry thickness is
100mm Mortar thickness is
10mm Cement consumption is 0.15 bags per cubic meter
Sand consumption is 0.35 cubic meter Now
we will see the block masonry The concrete
block masonry This is
concrete block masonry
The type and mix of masonry is written here
Cement quantity required in bags
Cement quantity required in kilograms
There is 200mm concrete block masonry
Mortar ratio is 1.76
Cement requirement is 0.124 bags per
cubic meter In kilograms
it is 6.2 kg per cubic meter Block masonry is 150mm thick
The mortar ratio is 1.26
Cement requirement is 0.093 bags per cubic meter
Cement requirement is 4.65 kg per cubic meter
Block masonry is 200mm thic
Mortar ratio is 1.24
Cement requirement is 0.206 bags per cubic meter
In kilograms it is 10.3 kg per cubic meter
Block masonry is 150mm thic
Cement requirement is 0.144 bags per cubic meter
Cement requirement is 7.2 kilograms per cubic meter
Block masonry is 100mm thic
Mortar ratio is 1.24
Cement requirement is 0.102 bags per cubic meter
In kilograms it is 5.15 kg per cubic meter
Now we will talk
about plastering Types of plastering
Cement quantity in bags
Cement quantity in kgs
These thumb rules are mainly for cement consumption
How much cement is kept in finishing activities
How many bags are stored per cubic meter And
how many kilograms are stored per cubic meter
Rough plastering
The cement requirement is 0.09 bags per cubic meter
In kilograms it is 4.5 kg per cubic meter
Internal wall plastering
Cement requirement is 0.09 bags per cubic meter
It is 4.5 kilograms per cubic meter
Duct plastering Cement requirement
is 0.09 bags per cubic meter
In kilograms it is 4.5 kg per cubic meter
External wall plastering
External wall plastering is generally of different thicknesses
Cement requirement is 0.175 bags per
cubic meter In kilograms it is 8.75
kg per cubic meter External wall plastering is generally done in 2 coats
So its cement consumption
is higher Stucco plastering
Cement requirement is 0.175 bags per cubic meter
It is 8.75 kg per cubic meter
Tiling wor
Anti-skid tiles consume 0.28 bags of cement per cubic meter
Ceramic tiles have a cement consumption of 0.3
bags per cubic meter Vitrepoid tile flooring
Vitrepoid tile flooring consumes 0.28 bags of cement per cubic meter
Vitrepoid tile Dado
Dado refers to wall tiles
Dado refers to vertical tiles in the kitchen and
bathroom Dado requires 0.27 bags of cement per cubic meter
Ceramic Dado has a cement consumption of 0.27
bags per cubic meter Dado has a cement consumption
of 0.27 bags per cubic meter
Natural stone flooring
Natural stone flooring uses 0.27 bags of cement per cubic meter
Marble flooring
Marble flooring uses 0.3 bags of cement per cubic meter
Marble baseboard
Baseboard has a cement consumption of 0.025 bags per cubic meter
Marble cladding
Marble cladding uses 0.27 bags of cement per cubic meter
Terracotta flooring
Terracotta tiles use 0.3 bags of cement per cubic meter
Manure tiles
Manure tiles use 0.3 bags of cement per cubic meter
Granologic flooring
Granuatic flooring has a cement consumption of 0.3 bags per cubic meter
Granular flooring uses 0.25 bags of cement per cubic meter
After that I also did door frame fixing on site where the cement is applied in the joint
There is a mortar joint and the cement consumption is 0.17 bags per square meter
Cement consumption is 0.17 bags per square meter
We will now discuss waterproofing and the amount of cement consumption required for it
If there is a sunken slab in the waterproofing then it is 0.25 bags per square meter
After that if it's for Agar waterproofing for walls then 0.25 bags per square meter
It is the waterproofing for the toilets and the sunken portion which would require 0.63 bags of cement per square meter
This cement consumption is in line with a standard thumb rule
If something different is mentioned in the drawing or atom description there might be some changes
We will now discuss the thumb rules for anti-termite treatment the chemicals used in anti-termite treatment
They are chloroperiform 20% of which remains and the rest is a 5-liter chemical
It is mixed with 95 liters of water and its usage is 7.5 liters per square meter
That means you can apply it over up to 7.5 square meters per liter
We will now discuss the thumb rule for calculating the painting area if you need to calculate the quantity or area of painting
And if you only have the carpet area you can use a simple formula
The paint area is equal to the carpet area multiplied by 3.5 meaning whatever the carpet area is you will multiply it by 3.5
It provides the quantity of paint area for the total flat with a note attached
This approximate paint area covers all walls and ceilings
So friend we saw the thumb rules for masonry and finishing works
as well as cement consumption for finishing works which activities do you mean
How much cement is needed per square meter how many bags of cement are needed
What did you think of today's video please leave a comment